Allegro Residences construction photos
62 photos from 8 site inspections, newest first. The percentage is how much of Allegro Residences was built on the day of each visit.
5 October 202684% built
4 August 202677% built
7 May 202670% built
5 March 202656% built
26 November 202535% built
4 August 202518% built
17 March 20256.1% built
29 November 20240% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.