Selora Residences construction progress
Selora Residences in Mohammed Bin Rashid Al Maktoum District 11 is 3.5% built at the Land Department inspection of September 2026. Developer Swank Real Estate Development. Completion registered for April 2027.
3.5%
Built, at the Land Department site inspection of 22 September 2026
Running behind its date
- Completion date (Land Department)
- April 2027
- Finish at recent pace
- April 2038
- Construction started
- May 2025
- Registered with the Land Department
- April 2025
- Developer
- Swank Real Estate Development
- Units
- 32
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- سيلورا ريزيدنسز
- Land Department project number
- 3573
- Land Department site inspections
- 3
Schedule
Between April 2026 and September 2026 the site added about 0.7 points a month. At that rate it would finish around April 2038, more than three months after the April 2027 date registered with the Land Department.
Site inspections
22 September 2026
3.5%+3.5 pts
23 April 2026
0%
3 March 2025
0%
Context
Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 26% built on average.
Swank Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Selora Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Selora Residences be completed?
- The completion date registered with the Dubai Land Department is April 2027. At the pace of its recent inspections the site would reach 100% around April 2038. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Selora Residences is built?
- 3.5%, measured at the Land Department site inspection on 22 September 2026. The Land Department engineers have inspected the site 3 times since March 2025.
- Is Selora Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
- Who is building Selora Residences?
- The registered developer is Swank Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Selora Residences?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Lua ResidencesAlso by Swank Real Estate Development. 64%, Due March 2026, passed.
- The Waterside Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 32%, Due June 2026, passed.
- The Lakeview Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 9.8%, Due August 2026, passed.
- The Woodland ResidencesNearby in Mohammed Bin Rashid Al Maktoum District 11. 75%.
- The Beachfront Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 35%, Due August 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.









