Selora Residences construction progress
The registered completion date for Selora Residences in Mohammed Bin Rashid Al Maktoum District 11 is April 2027. At the last site inspection, in September 2026, it was 3.5% built. The developer is Swank Real Estate Development.
3.5%
Built, at the site inspection of 22 September 2026
Running behind its date
- Registered completion date
- April 2027
- Finish at recent pace
- April 2038
- Construction started
- May 2025
- First registered
- April 2025
- Developer
- Swank Real Estate Development
- Units
- 32
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- سيلورا ريزيدنسز
- Project number
- 3573
- Site inspections
- 3
Schedule
Between April 2026 and September 2026 the site added about 0.7 points a month. At that rate it would finish around April 2038, more than three months after its registered date of April 2027.
Site inspections
22 September 2026
3.5%+3.5 pts
23 April 2026
0%
3 March 2025
0%
Context
Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.
Swank Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Selora Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Selora Residences handover date?
- The registered completion date is April 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2038. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Selora Residences?
- Selora Residences was 3.5% built at the site inspection on 22 September 2026. The site has been inspected 3 times since March 2025. The Land Department took 13 site photos at its inspections.
- Is Selora Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
- Who is building Selora Residences?
- The registered developer is Swank Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Selora Residences?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Lua ResidencesAlso by Swank Real Estate Development. 64%, Due March 2026, passed.
- The Waterside Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 45%, Due June 2026, passed.
- The Lakeview Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 20%, Due August 2026, passed.
- The Woodland ResidencesNearby in Mohammed Bin Rashid Al Maktoum District 11. 75%, Due April 2026, passed.
- The Beachfront Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 47%, Due August 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.