Selora Residences construction progress

Selora Residences in Mohammed Bin Rashid Al Maktoum District 11 is 3.5% built at the Land Department inspection of September 2026. Developer Swank Real Estate Development. Completion registered for April 2027.

3.5%

Built, at the Land Department site inspection of 22 September 2026

Running behind its date

Completion date (Land Department)
April 2027
Finish at recent pace
April 2038
Construction started
May 2025
Registered with the Land Department
April 2025
Developer
Swank Real Estate Development
Units
32
Escrow bank
Emirates Islamic Bank
Name in Arabic
سيلورا ريزيدنسز
Land Department project number
3573
Land Department site inspections
3

Schedule

Between April 2026 and September 2026 the site added about 0.7 points a month. At that rate it would finish around April 2038, more than three months after the April 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

22 September 2026

3.5%+3.5 pts

  • Selora Residences construction site, Land Department inspection photo 1, 22 September 2026
  • Selora Residences construction site, Land Department inspection photo 2, 22 September 2026
  • Selora Residences construction site, Land Department inspection photo 3, 22 September 2026
  • Selora Residences construction site, Land Department inspection photo 4, 22 September 2026

23 April 2026

0%

  • Selora Residences construction site, Land Department inspection photo 1, 23 April 2026
  • Selora Residences construction site, Land Department inspection photo 2, 23 April 2026
  • Selora Residences construction site, Land Department inspection photo 3, 23 April 2026
  • Selora Residences construction site, Land Department inspection photo 4, 23 April 2026

3 March 2025

0%

  • Selora Residences construction site, Land Department inspection photo 1, 3 March 2025
  • Selora Residences construction site, Land Department inspection photo 2, 3 March 2025

All 13 site photos, by inspection date

Context

Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 26% built on average.

Swank Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Selora Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Selora Residences be completed?
The completion date registered with the Dubai Land Department is April 2027. At the pace of its recent inspections the site would reach 100% around April 2038. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Selora Residences is built?
3.5%, measured at the Land Department site inspection on 22 September 2026. The Land Department engineers have inspected the site 3 times since March 2025.
Is Selora Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
Who is building Selora Residences?
The registered developer is Swank Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Selora Residences?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.