Selora Residences construction progress

The registered completion date for Selora Residences in Mohammed Bin Rashid Al Maktoum District 11 is April 2027. At the last site inspection, in September 2026, it was 3.5% built. The developer is Swank Real Estate Development.

3.5%

Built, at the site inspection of 22 September 2026

Running behind its date

Registered completion date
April 2027
Finish at recent pace
April 2038
Construction started
May 2025
First registered
April 2025
Developer
Swank Real Estate Development
Units
32
Escrow bank
Emirates Islamic Bank
Name in Arabic
سيلورا ريزيدنسز
Project number
3573
Site inspections
3

Schedule

Between April 2026 and September 2026 the site added about 0.7 points a month. At that rate it would finish around April 2038, more than three months after its registered date of April 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 September 2026

3.5%+3.5 pts

  • Selora Residences construction site, inspection photo 1, 22 September 2026
  • Selora Residences construction site, inspection photo 2, 22 September 2026
  • Selora Residences construction site, inspection photo 3, 22 September 2026
  • Selora Residences construction site, inspection photo 4, 22 September 2026

23 April 2026

0%

  • Selora Residences construction site, inspection photo 1, 23 April 2026
  • Selora Residences construction site, inspection photo 2, 23 April 2026
  • Selora Residences construction site, inspection photo 3, 23 April 2026
  • Selora Residences construction site, inspection photo 4, 23 April 2026

3 March 2025

0%

  • Selora Residences construction site, inspection photo 1, 3 March 2025
  • Selora Residences construction site, inspection photo 2, 3 March 2025

All 13 site photos, by inspection date

Context

Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.

Swank Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Selora Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Selora Residences handover date?
The registered completion date is April 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2038. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Selora Residences?
Selora Residences was 3.5% built at the site inspection on 22 September 2026. The site has been inspected 3 times since March 2025. The Land Department took 13 site photos at its inspections.
Is Selora Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
Who is building Selora Residences?
The registered developer is Swank Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Selora Residences?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.