Sukoon By Nuri construction progress

Sukoon By Nuri in Meydan Racecourse Community is 47% built at the Land Department inspection of June 2026. Developer Nuri Real Estate Development. Completion registered for December 2026.

47%

Built, at the Land Department site inspection of 30 June 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
October 2027
Construction started
May 2025
Registered with the Land Department
September 2025
Developer
Nuri Real Estate Development
Units
41
Escrow bank
Al Ahli Bank of Kuwait
Name in Arabic
سكون باي نوري
Land Department project number
3753
Land Department site inspections
4

Schedule

Between September 2025 and June 2026 the site added about 3.5 points a month. At that rate it would finish around October 2027, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%2026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 June 2026

47%+18 pts

  • Sukoon By Nuri construction site, Land Department inspection photo 1, 30 June 2026
  • Sukoon By Nuri construction site, Land Department inspection photo 2, 30 June 2026
  • Sukoon By Nuri construction site, Land Department inspection photo 3, 30 June 2026
  • Sukoon By Nuri construction site, Land Department inspection photo 4, 30 June 2026

20 February 2026

29%+16 pts

  • Sukoon By Nuri construction site, Land Department inspection photo 1, 20 February 2026
  • Sukoon By Nuri construction site, Land Department inspection photo 2, 20 February 2026
  • Sukoon By Nuri construction site, Land Department inspection photo 3, 20 February 2026
  • Sukoon By Nuri construction site, Land Department inspection photo 4, 20 February 2026

8 September 2025

13%+11 pts

  • Sukoon By Nuri construction site, Land Department inspection photo 1, 8 September 2025
  • Sukoon By Nuri construction site, Land Department inspection photo 2, 8 September 2025
  • Sukoon By Nuri construction site, Land Department inspection photo 3, 8 September 2025
  • Sukoon By Nuri construction site, Land Department inspection photo 4, 8 September 2025

15 June 2025

2.0%

  • Sukoon By Nuri construction site, Land Department inspection photo 1, 15 June 2025
  • Sukoon By Nuri construction site, Land Department inspection photo 2, 15 June 2025
  • Sukoon By Nuri construction site, Land Department inspection photo 3, 15 June 2025
  • Sukoon By Nuri construction site, Land Department inspection photo 4, 15 June 2025

All 24 site photos, by inspection date

Context

Meydan Racecourse Community has 9 projects under construction, 31% built on average. Sukoon By Nuri is ahead of that average.

Own a unit in Sukoon By Nuri?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Sukoon By Nuri be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around October 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Sukoon By Nuri is built?
47%, measured at the Land Department site inspection on 30 June 2026. The Land Department engineers have inspected the site 4 times since June 2025.
Is Sukoon By Nuri delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Sukoon By Nuri?
The registered developer is Nuri Real Estate Development.
Which bank holds the escrow account for Sukoon By Nuri?
Al Ahli Bank of Kuwait. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.