Sukoon By Nuri construction progress

The registered completion date for Sukoon By Nuri in Meydan Racecourse Community is December 2026. At the last site inspection, in June 2026, it was 47% built. The developer is Nuri Real Estate Development.

47%

Built, at the site inspection of 30 June 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
October 2027
Construction started
May 2025
First registered
September 2025
Developer
Nuri Real Estate Development
Units
41
Escrow bank
Al Ahli Bank of Kuwait
Name in Arabic
سكون باي نوري
Project number
3753
Site inspections
4

Schedule

Between September 2025 and June 2026 the site added about 3.5 points a month. At that rate it would finish around October 2027, more than three months after its registered date of December 2026.

0%25%50%75%100%2026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 June 2026

47%+18 pts

  • Sukoon By Nuri construction site, inspection photo 1, 30 June 2026
  • Sukoon By Nuri construction site, inspection photo 2, 30 June 2026
  • Sukoon By Nuri construction site, inspection photo 3, 30 June 2026
  • Sukoon By Nuri construction site, inspection photo 4, 30 June 2026

20 February 2026

29%+16 pts

  • Sukoon By Nuri construction site, inspection photo 1, 20 February 2026
  • Sukoon By Nuri construction site, inspection photo 2, 20 February 2026
  • Sukoon By Nuri construction site, inspection photo 3, 20 February 2026
  • Sukoon By Nuri construction site, inspection photo 4, 20 February 2026

8 September 2025

13%+11 pts

  • Sukoon By Nuri construction site, inspection photo 1, 8 September 2025
  • Sukoon By Nuri construction site, inspection photo 2, 8 September 2025
  • Sukoon By Nuri construction site, inspection photo 3, 8 September 2025
  • Sukoon By Nuri construction site, inspection photo 4, 8 September 2025

15 June 2025

2.0%

  • Sukoon By Nuri construction site, inspection photo 1, 15 June 2025
  • Sukoon By Nuri construction site, inspection photo 2, 15 June 2025
  • Sukoon By Nuri construction site, inspection photo 3, 15 June 2025
  • Sukoon By Nuri construction site, inspection photo 4, 15 June 2025

All 24 site photos, by inspection date

Context

Meydan Racecourse Community has 9 projects under construction, 31% built on average.

Own a unit in Sukoon By Nuri?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sukoon By Nuri handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sukoon By Nuri?
Sukoon By Nuri was 47% built at the site inspection on 30 June 2026. The site has been inspected 4 times since June 2025. The Land Department took 24 site photos at its inspections.
Is Sukoon By Nuri delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Sukoon By Nuri?
The registered developer is Nuri Real Estate Development.
Which bank holds the escrow account for Sukoon By Nuri?
Al Ahli Bank of Kuwait. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.