Azizi Riviera Beachfront construction progress
The register lists Azizi Riviera Beachfront in Meydan One Community as complete, with a registered completion date of December 2025. Its last site inspection on record was in December 2025. The developer is Azizi Developments.
100%
Built, at the site inspection of 29 December 2025
Construction complete
- Registered completion date
- December 2025
- Construction started
- April 2021
- First registered
- October 2021
- Developer
- Azizi Developments
- Community
- Meydan One Community
- Units
- 609
- Escrow bank
- Ajman Bank
- Name in Arabic
- عزيزي ريفييرا بيتش فرونت
- Project number
- 2297
- Site inspections
- 10
Schedule
The register lists Azizi Riviera Beachfront as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
29 December 2025
100%+15 pts
8 December 2025
85%+15 pts
19 August 2025
70%+11 pts
30 April 2025
58%+13 pts
10 December 2024
46%+25 pts
13 June 2024
21%+8.5 pts
19 May 2023
13%+6.7 pts
2 November 2022
5.9%+1.4 pts
28 April 2022
4.5%+2.0 pts
20 September 2021
2.5%
Context
Meydan One Community has 9 projects under construction, 76% built on average.
Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.
Own a unit in Azizi Riviera Beachfront?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Azizi Riviera Beachfront handover date?
- Construction of Azizi Riviera Beachfront is recorded as complete, with a registered completion date of December 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Azizi Riviera Beachfront?
- Azizi Riviera Beachfront was 100% built at the site inspection on 29 December 2025. The site has been inspected 10 times since September 2021. The Land Department took 63 site photos at its inspections.
- Is Azizi Riviera Beachfront delayed?
- The register lists construction as complete.
- Who is building Azizi Riviera Beachfront?
- The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Riviera Beachfront?
- Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)





.jpeg&w=3840&q=75)








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)