Skip to content

Azizi Riviera 69 construction progress

The register lists Azizi Riviera 69 in Meydan One Community as complete, with a registered completion date of March 2026. Its last site inspection on record was in November 2025. The developer is Azizi Developments.

100%

Built, at the site inspection of 27 November 2025

Construction complete

Registered completion date
March 2026
Construction started
March 2024
First registered
July 2024
Units
123
Escrow bank
Commercial Bank of Dubai
Name in Arabic
عزيزى ريفيرا 69
Project number
3012
Site inspections
5

Schedule

The register lists Azizi Riviera 69 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 November 2025

100%+5.0 pts

  • Azizi Riviera 69 construction site, inspection photo 1, 27 November 2025
  • Azizi Riviera 69 construction site, inspection photo 2, 27 November 2025
  • Azizi Riviera 69 construction site, inspection photo 3, 27 November 2025
  • Azizi Riviera 69 construction site, inspection photo 4, 27 November 2025

22 October 2025

95%+14 pts

  • Azizi Riviera 69 construction site, inspection photo 1, 22 October 2025
  • Azizi Riviera 69 construction site, inspection photo 2, 22 October 2025
  • Azizi Riviera 69 construction site, inspection photo 3, 22 October 2025
  • Azizi Riviera 69 construction site, inspection photo 4, 22 October 2025

25 June 2025

81%+22 pts

  • Azizi Riviera 69 construction site, inspection photo 1, 25 June 2025
  • Azizi Riviera 69 construction site, inspection photo 2, 25 June 2025
  • Azizi Riviera 69 construction site, inspection photo 3, 25 June 2025
  • Azizi Riviera 69 construction site, inspection photo 4, 25 June 2025

28 January 2025

59%+25 pts

  • Azizi Riviera 69 construction site, inspection photo 1, 28 January 2025
  • Azizi Riviera 69 construction site, inspection photo 2, 28 January 2025
  • Azizi Riviera 69 construction site, inspection photo 3, 28 January 2025
  • Azizi Riviera 69 construction site, inspection photo 4, 28 January 2025

30 April 2024

34%

  • Azizi Riviera 69 construction site, inspection photo 1, 30 April 2024
  • Azizi Riviera 69 construction site, inspection photo 2, 30 April 2024
  • Azizi Riviera 69 construction site, inspection photo 3, 30 April 2024
  • Azizi Riviera 69 construction site, inspection photo 4, 30 April 2024

All 41 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 69?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 69 handover date?
Construction of Azizi Riviera 69 is recorded as complete, with a registered completion date of March 2026. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Riviera 69?
Azizi Riviera 69 was 100% built at the site inspection on 27 November 2025. The site has been inspected 5 times since April 2024. The Land Department took 41 site photos at its inspections.
Is Azizi Riviera 69 delayed?
The register lists construction as complete.
Who is building Azizi Riviera 69?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 69?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.