Azizi Riviera 67 construction progress

The register lists Azizi Riviera 67 in Meydan One Community as complete, with a registered completion date of March 2025. Its last site inspection on record was in March 2025. The developer is Azizi Developments.

100%

Built, at the site inspection of 27 March 2025

Construction complete

Registered completion date
March 2025
Construction started
December 2023
First registered
February 2024
Units
198
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزى ريفيرا 67
Project number
2912
Site inspections
3

Schedule

The register lists Azizi Riviera 67 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 March 2025

100%+2.8 pts

  • Azizi Riviera 67 construction site, inspection photo 1, 27 March 2025
  • Azizi Riviera 67 construction site, inspection photo 2, 27 March 2025
  • Azizi Riviera 67 construction site, inspection photo 3, 27 March 2025
  • Azizi Riviera 67 construction site, inspection photo 4, 27 March 2025

19 November 2024

97%+46 pts

  • Azizi Riviera 67 construction site, inspection photo 1, 19 November 2024
  • Azizi Riviera 67 construction site, inspection photo 2, 19 November 2024
  • Azizi Riviera 67 construction site, inspection photo 3, 19 November 2024
  • Azizi Riviera 67 construction site, inspection photo 4, 19 November 2024

19 January 2024

51%

  • Azizi Riviera 67 construction site, inspection photo 1, 19 January 2024
  • Azizi Riviera 67 construction site, inspection photo 2, 19 January 2024
  • Azizi Riviera 67 construction site, inspection photo 3, 19 January 2024
  • Azizi Riviera 67 construction site, inspection photo 4, 19 January 2024

All 27 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 67?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 67 handover date?
Construction of Azizi Riviera 67 is recorded as complete, with a registered completion date of March 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Riviera 67?
Azizi Riviera 67 was 100% built at the site inspection on 27 March 2025. The site has been inspected 3 times since January 2024. The Land Department took 27 site photos at its inspections.
Is Azizi Riviera 67 delayed?
The register lists construction as complete.
Who is building Azizi Riviera 67?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 67?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.