Skip to content

Azizi Riviera 61 construction progress

The register lists Azizi Riviera 61 in Meydan One Community as complete, with a registered completion date of March 2025. Its last site inspection on record was in March 2025. The developer is Azizi Developments.

100%

Built, at the site inspection of 27 March 2025

Construction complete

Registered completion date
March 2025
Construction started
October 2023
First registered
December 2023
Units
240
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزى ريفيرا 61
Project number
2817
Site inspections
3

Schedule

The register lists Azizi Riviera 61 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 March 2025

100%+19 pts

  • Azizi Riviera 61 construction site, inspection photo 1, 27 March 2025
  • Azizi Riviera 61 construction site, inspection photo 2, 27 March 2025
  • Azizi Riviera 61 construction site, inspection photo 3, 27 March 2025
  • Azizi Riviera 61 construction site, inspection photo 4, 27 March 2025

13 June 2024

81%+43 pts

  • Azizi Riviera 61 construction site, inspection photo 1, 13 June 2024
  • Azizi Riviera 61 construction site, inspection photo 2, 13 June 2024
  • Azizi Riviera 61 construction site, inspection photo 3, 13 June 2024
  • Azizi Riviera 61 construction site, inspection photo 4, 13 June 2024

31 October 2023

37%

  • Azizi Riviera 61 construction site, inspection photo 1, 31 October 2023
  • Azizi Riviera 61 construction site, inspection photo 2, 31 October 2023
  • Azizi Riviera 61 construction site, inspection photo 3, 31 October 2023
  • Azizi Riviera 61 construction site, inspection photo 4, 31 October 2023

All 27 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 61?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 61 handover date?
Construction of Azizi Riviera 61 is recorded as complete, with a registered completion date of March 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Riviera 61?
Azizi Riviera 61 was 100% built at the site inspection on 27 March 2025. The site has been inspected 3 times since October 2023. The Land Department took 27 site photos at its inspections.
Is Azizi Riviera 61 delayed?
The register lists construction as complete.
Who is building Azizi Riviera 61?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 61?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.