Azizi Riviera 60 construction progress

Azizi Riviera 60 in Meydan One Community is 97% built at the Land Department inspection of September 2026. Developer Azizi Developments. Completion registered for March 2027.

97%

Built, at the Land Department site inspection of 15 September 2026

On pace for its date

Completion date (Land Department)
March 2027
Finish at recent pace
October 2026
Construction started
March 2025
Registered with the Land Department
June 2025
Units
87
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
60 عزيزي ريفيرا
Land Department project number
3618
Land Department site inspections
4

Schedule

Since January 2026 Azizi Riviera 60 has added about 2.8 points a month. That puts 100% around October 2026, within three months of its registered completion date of March 2027.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

15 September 2026

97%+22 pts

  • Azizi Riviera 60 construction site, Land Department inspection photo 1, 15 September 2026
  • Azizi Riviera 60 construction site, Land Department inspection photo 2, 15 September 2026
  • Azizi Riviera 60 construction site, Land Department inspection photo 3, 15 September 2026
  • Azizi Riviera 60 construction site, Land Department inspection photo 4, 15 September 2026

21 January 2026

75%+21 pts

  • Azizi Riviera 60 construction site, Land Department inspection photo 1, 21 January 2026
  • Azizi Riviera 60 construction site, Land Department inspection photo 2, 21 January 2026
  • Azizi Riviera 60 construction site, Land Department inspection photo 3, 21 January 2026
  • Azizi Riviera 60 construction site, Land Department inspection photo 4, 21 January 2026

12 September 2025

54%+21 pts

  • Azizi Riviera 60 construction site, Land Department inspection photo 1, 12 September 2025
  • Azizi Riviera 60 construction site, Land Department inspection photo 2, 12 September 2025
  • Azizi Riviera 60 construction site, Land Department inspection photo 3, 12 September 2025
  • Azizi Riviera 60 construction site, Land Department inspection photo 4, 12 September 2025

8 April 2025

34%

  • Azizi Riviera 60 construction site, Land Department inspection photo 1, 8 April 2025
  • Azizi Riviera 60 construction site, Land Department inspection photo 2, 8 April 2025
  • Azizi Riviera 60 construction site, Land Department inspection photo 3, 8 April 2025
  • Azizi Riviera 60 construction site, Land Department inspection photo 4, 8 April 2025

All 35 site photos, by inspection date

Context

Meydan One Community has 10 projects under construction, 77% built on average.

Azizi Developments has 57 projects under construction in Dubai; 9 have passed their registered completion date.

Own a unit in Azizi Riviera 60?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Azizi Riviera 60 be completed?
The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around October 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Azizi Riviera 60 is built?
97%, measured at the Land Department site inspection on 15 September 2026. The Land Department engineers have inspected the site 4 times since April 2025.
Is Azizi Riviera 60 delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2027.
Who is building Azizi Riviera 60?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 60?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.