Skip to content

Azizi Riviera 56 construction progress

The register lists Azizi Riviera 56 in Meydan One Community as complete, with a registered completion date of March 2027. Its last site inspection on record was in April 2026. The developer is Azizi Developments.

100%

Built, at the site inspection of 28 April 2026

Construction complete

Registered completion date
March 2027
Construction started
March 2025
First registered
May 2025
Units
87
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي ريفيرا 56
Project number
3617
Site inspections
4

Schedule

The register lists Azizi Riviera 56 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 April 2026

100%+21 pts

  • Azizi Riviera 56 construction site, inspection photo 1, 28 April 2026
  • Azizi Riviera 56 construction site, inspection photo 2, 28 April 2026
  • Azizi Riviera 56 construction site, inspection photo 3, 28 April 2026
  • Azizi Riviera 56 construction site, inspection photo 4, 28 April 2026

21 January 2026

79%+12 pts

  • Azizi Riviera 56 construction site, inspection photo 1, 21 January 2026
  • Azizi Riviera 56 construction site, inspection photo 2, 21 January 2026
  • Azizi Riviera 56 construction site, inspection photo 3, 21 January 2026
  • Azizi Riviera 56 construction site, inspection photo 4, 21 January 2026

12 September 2025

68%+20 pts

  • Azizi Riviera 56 construction site, inspection photo 1, 12 September 2025
  • Azizi Riviera 56 construction site, inspection photo 2, 12 September 2025
  • Azizi Riviera 56 construction site, inspection photo 3, 12 September 2025
  • Azizi Riviera 56 construction site, inspection photo 4, 12 September 2025

8 April 2025

48%

  • Azizi Riviera 56 construction site, inspection photo 1, 8 April 2025
  • Azizi Riviera 56 construction site, inspection photo 2, 8 April 2025
  • Azizi Riviera 56 construction site, inspection photo 3, 8 April 2025
  • Azizi Riviera 56 construction site, inspection photo 4, 8 April 2025

All 41 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 56?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 56 handover date?
Construction of Azizi Riviera 56 is recorded as complete, with a registered completion date of March 2027. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Riviera 56?
Azizi Riviera 56 was 100% built at the site inspection on 28 April 2026. The site has been inspected 4 times since April 2025. The Land Department took 41 site photos at its inspections.
Is Azizi Riviera 56 delayed?
The register lists construction as complete.
Who is building Azizi Riviera 56?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 56?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.