Azizi Riviera 5 construction progress

The register lists Azizi Riviera 5 in Meydan One Community as complete, with a registered completion date of May 2023. Its last site inspection on record was in May 2023. The developer is Azizi Developments.

100%

Built, at the site inspection of 25 May 2023

Construction complete

Registered completion date
May 2023
Construction started
July 2017
First registered
July 2017
Units
221
Escrow bank
Ajman Bank
Name in Arabic
5 عزيزي ريفيرا
Project number
1927
Site inspections
12

Schedule

The register lists Azizi Riviera 5 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820202022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 May 2023

100%+11 pts

  • Azizi Riviera 5 construction site, inspection photo 1, 25 May 2023
  • Azizi Riviera 5 construction site, inspection photo 2, 25 May 2023
  • Azizi Riviera 5 construction site, inspection photo 3, 25 May 2023
  • Azizi Riviera 5 construction site, inspection photo 4, 25 May 2023

24 March 2022

89%+6.2 pts

  • Azizi Riviera 5 construction site, inspection photo 1, 24 March 2022
  • Azizi Riviera 5 construction site, inspection photo 2, 24 March 2022
  • Azizi Riviera 5 construction site, inspection photo 3, 24 March 2022
  • Azizi Riviera 5 construction site, inspection photo 4, 24 March 2022

18 October 2021

82%+9.5 pts

  • Azizi Riviera 5 construction site, inspection photo 1, 18 October 2021
  • Azizi Riviera 5 construction site, inspection photo 2, 18 October 2021
  • Azizi Riviera 5 construction site, inspection photo 3, 18 October 2021
  • Azizi Riviera 5 construction site, inspection photo 4, 18 October 2021

5 April 2021

73%+11 pts

  • Azizi Riviera 5 construction site, inspection photo 1, 5 April 2021
  • Azizi Riviera 5 construction site, inspection photo 2, 5 April 2021
  • Azizi Riviera 5 construction site, inspection photo 3, 5 April 2021
  • Azizi Riviera 5 construction site, inspection photo 4, 5 April 2021

10 November 2020

62%+9.9 pts

  • Azizi Riviera 5 construction site, inspection photo 1, 10 November 2020
  • Azizi Riviera 5 construction site, inspection photo 2, 10 November 2020
  • Azizi Riviera 5 construction site, inspection photo 3, 10 November 2020
  • Azizi Riviera 5 construction site, inspection photo 4, 10 November 2020

14 July 2020

52%+1.6 pts

  • Azizi Riviera 5 construction site, inspection photo 1, 14 July 2020
  • Azizi Riviera 5 construction site, inspection photo 2, 14 July 2020
  • Azizi Riviera 5 construction site, inspection photo 3, 14 July 2020
  • Azizi Riviera 5 construction site, inspection photo 4, 14 July 2020

17 June 2020

51%+4.5 pts

  • Azizi Riviera 5 construction site, inspection photo 1, 17 June 2020
  • Azizi Riviera 5 construction site, inspection photo 2, 17 June 2020
  • Azizi Riviera 5 construction site, inspection photo 3, 17 June 2020
  • Azizi Riviera 5 construction site, inspection photo 4, 17 June 2020

10 February 2020

46%+10 pts

  • Azizi Riviera 5 construction site, inspection photo 1, 10 February 2020
  • Azizi Riviera 5 construction site, inspection photo 2, 10 February 2020
  • Azizi Riviera 5 construction site, inspection photo 3, 10 February 2020
  • Azizi Riviera 5 construction site, inspection photo 4, 10 February 2020

9 July 2019

36%+10 pts

  • Azizi Riviera 5 construction site, inspection photo 1, 9 July 2019
  • Azizi Riviera 5 construction site, inspection photo 2, 9 July 2019
  • Azizi Riviera 5 construction site, inspection photo 3, 9 July 2019
  • Azizi Riviera 5 construction site, inspection photo 4, 9 July 2019

3 January 2019

26%+5.5 pts

  • Azizi Riviera 5 construction site, inspection photo 1, 3 January 2019
  • Azizi Riviera 5 construction site, inspection photo 2, 3 January 2019
  • Azizi Riviera 5 construction site, inspection photo 3, 3 January 2019
  • Azizi Riviera 5 construction site, inspection photo 4, 3 January 2019

All 115 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 5?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 5 handover date?
Construction of Azizi Riviera 5 is recorded as complete, with a registered completion date of May 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Riviera 5?
Azizi Riviera 5 was 100% built at the site inspection on 25 May 2023. The site has been inspected 12 times since April 2018. The Land Department took 115 site photos at its inspections.
Is Azizi Riviera 5 delayed?
The register lists construction as complete.
Who is building Azizi Riviera 5?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 5?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.