Skip to content

Azizi Riviera 44 construction progress

The register lists Azizi Riviera 44 in Meydan One Community as complete, with a registered completion date of January 2024. Its last site inspection on record was in January 2024. The developer is Azizi Developments.

100%

Built, at the site inspection of 18 January 2024

Construction complete

Registered completion date
January 2024
Construction started
November 2020
First registered
November 2021
Units
279
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي ريفييرا 44
Project number
2296
Site inspections
6

Schedule

The register lists Azizi Riviera 44 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2021202220232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 January 2024

100%+1.8 pts

  • Azizi Riviera 44 construction site, inspection photo 1, 18 January 2024
  • Azizi Riviera 44 construction site, inspection photo 2, 18 January 2024
  • Azizi Riviera 44 construction site, inspection photo 3, 18 January 2024
  • Azizi Riviera 44 construction site, inspection photo 4, 18 January 2024

7 November 2023

98%+6.1 pts

  • Azizi Riviera 44 construction site, inspection photo 1, 7 November 2023
  • Azizi Riviera 44 construction site, inspection photo 2, 7 November 2023
  • Azizi Riviera 44 construction site, inspection photo 3, 7 November 2023
  • Azizi Riviera 44 construction site, inspection photo 4, 7 November 2023

31 May 2023

92%+25 pts

  • Azizi Riviera 44 construction site, inspection photo 1, 31 May 2023
  • Azizi Riviera 44 construction site, inspection photo 2, 31 May 2023
  • Azizi Riviera 44 construction site, inspection photo 3, 31 May 2023
  • Azizi Riviera 44 construction site, inspection photo 4, 31 May 2023

2 November 2022

67%+23 pts

  • Azizi Riviera 44 construction site, inspection photo 1, 2 November 2022
  • Azizi Riviera 44 construction site, inspection photo 2, 2 November 2022
  • Azizi Riviera 44 construction site, inspection photo 3, 2 November 2022
  • Azizi Riviera 44 construction site, inspection photo 4, 2 November 2022

28 April 2022

44%+11 pts

  • Azizi Riviera 44 construction site, inspection photo 1, 28 April 2022
  • Azizi Riviera 44 construction site, inspection photo 2, 28 April 2022
  • Azizi Riviera 44 construction site, inspection photo 3, 28 April 2022
  • Azizi Riviera 44 construction site, inspection photo 4, 28 April 2022

20 September 2021

32%

  • Azizi Riviera 44 construction site, inspection photo 1, 20 September 2021
  • Azizi Riviera 44 construction site, inspection photo 2, 20 September 2021
  • Azizi Riviera 44 construction site, inspection photo 3, 20 September 2021
  • Azizi Riviera 44 construction site, inspection photo 4, 20 September 2021

All 54 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 44?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 44 handover date?
Construction of Azizi Riviera 44 is recorded as complete, with a registered completion date of January 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Riviera 44?
Azizi Riviera 44 was 100% built at the site inspection on 18 January 2024. The site has been inspected 6 times since September 2021. The Land Department took 54 site photos at its inspections.
Is Azizi Riviera 44 delayed?
The register lists construction as complete.
Who is building Azizi Riviera 44?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 44?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.