Skip to content

Azizi Riviera 42 construction progress

The register lists Azizi Riviera 42 in Meydan One Community as complete, with a registered completion date of January 2024. Its last site inspection on record was in January 2024. The developer is Azizi Developments.

100%

Built, at the site inspection of 18 January 2024

Construction complete

Registered completion date
January 2024
Construction started
November 2020
First registered
May 2022
Units
185
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي ريفييرا 42
Project number
2341
Site inspections
4

Schedule

The register lists Azizi Riviera 42 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2021202220232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

18 January 2024

100%+22 pts

  • Azizi Riviera 42 construction site, inspection photo 1, 18 January 2024
  • Azizi Riviera 42 construction site, inspection photo 2, 18 January 2024
  • Azizi Riviera 42 construction site, inspection photo 3, 18 January 2024
  • Azizi Riviera 42 construction site, inspection photo 4, 18 January 2024

27 July 2023

78%+22 pts

  • Azizi Riviera 42 construction site, inspection photo 1, 27 July 2023
  • Azizi Riviera 42 construction site, inspection photo 2, 27 July 2023
  • Azizi Riviera 42 construction site, inspection photo 3, 27 July 2023
  • Azizi Riviera 42 construction site, inspection photo 4, 27 July 2023

17 August 2022

56%+18 pts

  • Azizi Riviera 42 construction site, inspection photo 1, 17 August 2022
  • Azizi Riviera 42 construction site, inspection photo 2, 17 August 2022
  • Azizi Riviera 42 construction site, inspection photo 3, 17 August 2022
  • Azizi Riviera 42 construction site, inspection photo 4, 17 August 2022

12 January 2022

38%

  • Azizi Riviera 42 construction site, inspection photo 1, 12 January 2022
  • Azizi Riviera 42 construction site, inspection photo 2, 12 January 2022
  • Azizi Riviera 42 construction site, inspection photo 3, 12 January 2022
  • Azizi Riviera 42 construction site, inspection photo 4, 12 January 2022

All 36 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 42?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 42 handover date?
Construction of Azizi Riviera 42 is recorded as complete, with a registered completion date of January 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Riviera 42?
Azizi Riviera 42 was 100% built at the site inspection on 18 January 2024. The site has been inspected 4 times since January 2022. The Land Department took 36 site photos at its inspections.
Is Azizi Riviera 42 delayed?
The register lists construction as complete.
Who is building Azizi Riviera 42?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 42?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.