Skip to content

Azizi Riviera 4 construction progress

The register lists Azizi Riviera 4 in Meydan One Community as complete, with a registered completion date of September 2022. Its last site inspection on record was in October 2022. The developer is Azizi Developments.

100%

Built, at the site inspection of 31 October 2022

Construction complete

Registered completion date
September 2022
Construction started
October 2017
First registered
September 2017
Units
212
Escrow bank
Ajman Bank
Name in Arabic
عزيزي ريفييرا 4
Project number
1942
Site inspections
10

Schedule

The register lists Azizi Riviera 4 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20182019202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

31 October 2022

100%+9.8 pts

  • Azizi Riviera 4 construction site, inspection photo 1, 31 October 2022
  • Azizi Riviera 4 construction site, inspection photo 2, 31 October 2022
  • Azizi Riviera 4 construction site, inspection photo 3, 31 October 2022
  • Azizi Riviera 4 construction site, inspection photo 4, 31 October 2022

24 March 2022

90%+9.9 pts

  • Azizi Riviera 4 construction site, inspection photo 1, 24 March 2022
  • Azizi Riviera 4 construction site, inspection photo 2, 24 March 2022
  • Azizi Riviera 4 construction site, inspection photo 3, 24 March 2022
  • Azizi Riviera 4 construction site, inspection photo 4, 24 March 2022

18 October 2021

80%+14 pts

  • Azizi Riviera 4 construction site, inspection photo 1, 18 October 2021
  • Azizi Riviera 4 construction site, inspection photo 2, 18 October 2021
  • Azizi Riviera 4 construction site, inspection photo 3, 18 October 2021
  • Azizi Riviera 4 construction site, inspection photo 4, 18 October 2021

29 March 2021

66%+13 pts

  • Azizi Riviera 4 construction site, inspection photo 1, 29 March 2021
  • Azizi Riviera 4 construction site, inspection photo 2, 29 March 2021
  • Azizi Riviera 4 construction site, inspection photo 3, 29 March 2021
  • Azizi Riviera 4 construction site, inspection photo 4, 29 March 2021

1 October 2020

54%+7.9 pts

  • Azizi Riviera 4 construction site, inspection photo 1, 1 October 2020
  • Azizi Riviera 4 construction site, inspection photo 2, 1 October 2020
  • Azizi Riviera 4 construction site, inspection photo 3, 1 October 2020
  • Azizi Riviera 4 construction site, inspection photo 4, 1 October 2020

6 February 2020

46%+14 pts

  • Azizi Riviera 4 construction site, inspection photo 1, 6 February 2020
  • Azizi Riviera 4 construction site, inspection photo 2, 6 February 2020
  • Azizi Riviera 4 construction site, inspection photo 3, 6 February 2020
  • Azizi Riviera 4 construction site, inspection photo 4, 6 February 2020

9 July 2019

32%+8.4 pts

  • Azizi Riviera 4 construction site, inspection photo 1, 9 July 2019
  • Azizi Riviera 4 construction site, inspection photo 2, 9 July 2019
  • Azizi Riviera 4 construction site, inspection photo 3, 9 July 2019
  • Azizi Riviera 4 construction site, inspection photo 4, 9 July 2019

10 April 2019

23%+4.4 pts

  • Azizi Riviera 4 construction site, inspection photo 1, 10 April 2019
  • Azizi Riviera 4 construction site, inspection photo 2, 10 April 2019
  • Azizi Riviera 4 construction site, inspection photo 3, 10 April 2019
  • Azizi Riviera 4 construction site, inspection photo 4, 10 April 2019

3 January 2019

19%+16 pts

  • Azizi Riviera 4 construction site, inspection photo 1, 3 January 2019
  • Azizi Riviera 4 construction site, inspection photo 2, 3 January 2019
  • Azizi Riviera 4 construction site, inspection photo 3, 3 January 2019
  • Azizi Riviera 4 construction site, inspection photo 4, 3 January 2019

3 April 2018

3.2%

  • Azizi Riviera 4 construction site, inspection photo 1, 3 April 2018
  • Azizi Riviera 4 construction site, inspection photo 2, 3 April 2018
  • Azizi Riviera 4 construction site, inspection photo 3, 3 April 2018
  • Azizi Riviera 4 construction site, inspection photo 4, 3 April 2018

All 105 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 4?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 4 handover date?
Construction of Azizi Riviera 4 is recorded as complete, with a registered completion date of September 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Riviera 4?
Azizi Riviera 4 was 100% built at the site inspection on 31 October 2022. The site has been inspected 10 times since April 2018. The Land Department took 105 site photos at its inspections.
Is Azizi Riviera 4 delayed?
The register lists construction as complete.
Who is building Azizi Riviera 4?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 4?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.