Azizi Riviera 4 construction progress
The register lists Azizi Riviera 4 in Meydan One Community as complete, with a registered completion date of September 2022. Its last site inspection on record was in October 2022. The developer is Azizi Developments.
100%
Built, at the site inspection of 31 October 2022
Construction complete
- Registered completion date
- September 2022
- Construction started
- October 2017
- First registered
- September 2017
- Developer
- Azizi Developments
- Community
- Meydan One Community
- Units
- 212
- Escrow bank
- Ajman Bank
- Name in Arabic
- عزيزي ريفييرا 4
- Project number
- 1942
- Site inspections
- 10
Schedule
The register lists Azizi Riviera 4 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
31 October 2022
100%+9.8 pts
24 March 2022
90%+9.9 pts
18 October 2021
80%+14 pts
29 March 2021
66%+13 pts
1 October 2020
54%+7.9 pts
6 February 2020
46%+14 pts
9 July 2019
32%+8.4 pts
10 April 2019
23%+4.4 pts
3 January 2019
19%+16 pts
3 April 2018
3.2%
Context
Meydan One Community has 9 projects under construction, 76% built on average.
Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.
Own a unit in Azizi Riviera 4?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Azizi Riviera 4 handover date?
- Construction of Azizi Riviera 4 is recorded as complete, with a registered completion date of September 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Azizi Riviera 4?
- Azizi Riviera 4 was 100% built at the site inspection on 31 October 2022. The site has been inspected 10 times since April 2018. The Land Department took 105 site photos at its inspections.
- Is Azizi Riviera 4 delayed?
- The register lists construction as complete.
- Who is building Azizi Riviera 4?
- The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
- Which bank holds the escrow account for Azizi Riviera 4?
- Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)