Azizi Riviera 39 construction progress

The register lists Azizi Riviera 39 in Meydan One Community as complete, with a registered completion date of March 2024. Its last site inspection on record was in March 2024. The developer is Azizi Developments.

100%

Built, at the site inspection of 4 March 2024

Construction complete

Registered completion date
March 2024
Construction started
December 2018
First registered
December 2018
Units
171
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي ريفيرا 39
Project number
2124
Site inspections
8

Schedule

The register lists Azizi Riviera 39 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201920212023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 March 2024

100%+10.0 pts

  • Azizi Riviera 39 construction site, inspection photo 1, 4 March 2024
  • Azizi Riviera 39 construction site, inspection photo 2, 4 March 2024
  • Azizi Riviera 39 construction site, inspection photo 3, 4 March 2024
  • Azizi Riviera 39 construction site, inspection photo 4, 4 March 2024

10 May 2023

90%+12 pts

  • Azizi Riviera 39 construction site, inspection photo 1, 10 May 2023
  • Azizi Riviera 39 construction site, inspection photo 2, 10 May 2023
  • Azizi Riviera 39 construction site, inspection photo 3, 10 May 2023
  • Azizi Riviera 39 construction site, inspection photo 4, 10 May 2023

21 November 2022

78%+12 pts

  • Azizi Riviera 39 construction site, inspection photo 1, 21 November 2022
  • Azizi Riviera 39 construction site, inspection photo 2, 21 November 2022
  • Azizi Riviera 39 construction site, inspection photo 3, 21 November 2022
  • Azizi Riviera 39 construction site, inspection photo 4, 21 November 2022

29 June 2022

66%+16 pts

  • Azizi Riviera 39 construction site, inspection photo 1, 29 June 2022
  • Azizi Riviera 39 construction site, inspection photo 2, 29 June 2022
  • Azizi Riviera 39 construction site, inspection photo 3, 29 June 2022
  • Azizi Riviera 39 construction site, inspection photo 4, 29 June 2022

12 January 2022

50%+9.0 pts

  • Azizi Riviera 39 construction site, inspection photo 1, 12 January 2022
  • Azizi Riviera 39 construction site, inspection photo 2, 12 January 2022
  • Azizi Riviera 39 construction site, inspection photo 3, 12 January 2022
  • Azizi Riviera 39 construction site, inspection photo 4, 12 January 2022

30 August 2021

41%+23 pts

  • Azizi Riviera 39 construction site, inspection photo 1, 30 August 2021
  • Azizi Riviera 39 construction site, inspection photo 2, 30 August 2021
  • Azizi Riviera 39 construction site, inspection photo 3, 30 August 2021
  • Azizi Riviera 39 construction site, inspection photo 4, 30 August 2021

24 December 2020

18%+8.3 pts

  • Azizi Riviera 39 construction site, inspection photo 1, 24 December 2020
  • Azizi Riviera 39 construction site, inspection photo 2, 24 December 2020
  • Azizi Riviera 39 construction site, inspection photo 3, 24 December 2020
  • Azizi Riviera 39 construction site, inspection photo 4, 24 December 2020

16 December 2019

9.4%

  • Azizi Riviera 39 construction site, inspection photo 1, 16 December 2019
  • Azizi Riviera 39 construction site, inspection photo 2, 16 December 2019
  • Azizi Riviera 39 construction site, inspection photo 3, 16 December 2019
  • Azizi Riviera 39 construction site, inspection photo 4, 16 December 2019

All 61 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 39?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 39 handover date?
Construction of Azizi Riviera 39 is recorded as complete, with a registered completion date of March 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Riviera 39?
Azizi Riviera 39 was 100% built at the site inspection on 4 March 2024. The site has been inspected 8 times since December 2019. The Land Department took 61 site photos at its inspections.
Is Azizi Riviera 39 delayed?
The register lists construction as complete.
Who is building Azizi Riviera 39?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 39?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.