Skip to content

Azizi Riviera 32 construction progress

The register lists Azizi Riviera 32 in Meydan One Community as complete, with a registered completion date of June 2023. Its last site inspection on record was in September 2023. The developer is Azizi Developments.

100%

Built, at the site inspection of 13 September 2023

Construction complete

Registered completion date
June 2023
Construction started
October 2017
First registered
March 2018
Units
247
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي ريفييرا 32
Project number
2042
Site inspections
9

Schedule

The register lists Azizi Riviera 32 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820202022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 September 2023

100%+23 pts

  • Azizi Riviera 32 construction site, inspection photo 1, 13 September 2023
  • Azizi Riviera 32 construction site, inspection photo 2, 13 September 2023
  • Azizi Riviera 32 construction site, inspection photo 3, 13 September 2023
  • Azizi Riviera 32 construction site, inspection photo 4, 13 September 2023

18 July 2022

77%+9.6 pts

  • Azizi Riviera 32 construction site, inspection photo 1, 18 July 2022
  • Azizi Riviera 32 construction site, inspection photo 2, 18 July 2022
  • Azizi Riviera 32 construction site, inspection photo 3, 18 July 2022
  • Azizi Riviera 32 construction site, inspection photo 4, 18 July 2022

5 December 2021

68%+15 pts

  • Azizi Riviera 32 construction site, inspection photo 1, 5 December 2021
  • Azizi Riviera 32 construction site, inspection photo 2, 5 December 2021
  • Azizi Riviera 32 construction site, inspection photo 3, 5 December 2021
  • Azizi Riviera 32 construction site, inspection photo 4, 5 December 2021

14 June 2021

52%+8.3 pts

  • Azizi Riviera 32 construction site, inspection photo 1, 14 June 2021
  • Azizi Riviera 32 construction site, inspection photo 2, 14 June 2021
  • Azizi Riviera 32 construction site, inspection photo 3, 14 June 2021
  • Azizi Riviera 32 construction site, inspection photo 4, 14 June 2021

19 January 2021

44%+20 pts

  • Azizi Riviera 32 construction site, inspection photo 1, 19 January 2021
  • Azizi Riviera 32 construction site, inspection photo 2, 19 January 2021
  • Azizi Riviera 32 construction site, inspection photo 3, 19 January 2021
  • Azizi Riviera 32 construction site, inspection photo 4, 19 January 2021

17 February 2020

24%+1.5 pts

  • Azizi Riviera 32 construction site, inspection photo 1, 17 February 2020
  • Azizi Riviera 32 construction site, inspection photo 2, 17 February 2020
  • Azizi Riviera 32 construction site, inspection photo 3, 17 February 2020
  • Azizi Riviera 32 construction site, inspection photo 4, 17 February 2020

15 January 2020

23%+4.6 pts

  • Azizi Riviera 32 construction site, inspection photo 1, 15 January 2020
  • Azizi Riviera 32 construction site, inspection photo 2, 15 January 2020
  • Azizi Riviera 32 construction site, inspection photo 3, 15 January 2020
  • Azizi Riviera 32 construction site, inspection photo 4, 15 January 2020

26 November 2019

18%+3.1 pts

  • Azizi Riviera 32 construction site, inspection photo 1, 26 November 2019
  • Azizi Riviera 32 construction site, inspection photo 2, 26 November 2019
  • Azizi Riviera 32 construction site, inspection photo 3, 26 November 2019
  • Azizi Riviera 32 construction site, inspection photo 4, 26 November 2019

5 September 2019

15%

  • Azizi Riviera 32 construction site, inspection photo 1, 5 September 2019
  • Azizi Riviera 32 construction site, inspection photo 2, 5 September 2019
  • Azizi Riviera 32 construction site, inspection photo 3, 5 September 2019
  • Azizi Riviera 32 construction site, inspection photo 4, 5 September 2019

All 81 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 32?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 32 handover date?
Construction of Azizi Riviera 32 is recorded as complete, with a registered completion date of June 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Riviera 32?
Azizi Riviera 32 was 100% built at the site inspection on 13 September 2023. The site has been inspected 9 times since September 2019. The Land Department took 81 site photos at its inspections.
Is Azizi Riviera 32 delayed?
The register lists construction as complete.
Who is building Azizi Riviera 32?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 32?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.