Azizi Riviera 31 construction progress

The register lists Azizi Riviera 31 in Meydan One Community as complete, with a registered completion date of June 2023. Its last site inspection on record was in September 2023. The developer is Azizi Developments.

100%

Built, at the site inspection of 13 September 2023

Construction complete

Registered completion date
June 2023
Construction started
April 2018
First registered
March 2021
Units
134
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي ريفيرا 31
Project number
2231
Site inspections
6

Schedule

The register lists Azizi Riviera 31 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20192020202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 September 2023

100%+2.0 pts

  • Azizi Riviera 31 construction site, inspection photo 1, 13 September 2023
  • Azizi Riviera 31 construction site, inspection photo 2, 13 September 2023
  • Azizi Riviera 31 construction site, inspection photo 3, 13 September 2023
  • Azizi Riviera 31 construction site, inspection photo 4, 13 September 2023

27 March 2023

98%+22 pts

  • Azizi Riviera 31 construction site, inspection photo 1, 27 March 2023
  • Azizi Riviera 31 construction site, inspection photo 2, 27 March 2023
  • Azizi Riviera 31 construction site, inspection photo 3, 27 March 2023
  • Azizi Riviera 31 construction site, inspection photo 4, 27 March 2023

18 July 2022

76%+12 pts

  • Azizi Riviera 31 construction site, inspection photo 1, 18 July 2022
  • Azizi Riviera 31 construction site, inspection photo 2, 18 July 2022
  • Azizi Riviera 31 construction site, inspection photo 3, 18 July 2022
  • Azizi Riviera 31 construction site, inspection photo 4, 18 July 2022

5 December 2021

64%+13 pts

  • Azizi Riviera 31 construction site, inspection photo 1, 5 December 2021
  • Azizi Riviera 31 construction site, inspection photo 2, 5 December 2021
  • Azizi Riviera 31 construction site, inspection photo 3, 5 December 2021
  • Azizi Riviera 31 construction site, inspection photo 4, 5 December 2021

29 June 2021

51%+9.3 pts

  • Azizi Riviera 31 construction site, inspection photo 1, 29 June 2021
  • Azizi Riviera 31 construction site, inspection photo 2, 29 June 2021
  • Azizi Riviera 31 construction site, inspection photo 3, 29 June 2021
  • Azizi Riviera 31 construction site, inspection photo 4, 29 June 2021

18 February 2021

42%

  • Azizi Riviera 31 construction site, inspection photo 1, 18 February 2021
  • Azizi Riviera 31 construction site, inspection photo 2, 18 February 2021
  • Azizi Riviera 31 construction site, inspection photo 3, 18 February 2021
  • Azizi Riviera 31 construction site, inspection photo 4, 18 February 2021

All 63 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 31?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 31 handover date?
Construction of Azizi Riviera 31 is recorded as complete, with a registered completion date of June 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Riviera 31?
Azizi Riviera 31 was 100% built at the site inspection on 13 September 2023. The site has been inspected 6 times since February 2021. The Land Department took 63 site photos at its inspections.
Is Azizi Riviera 31 delayed?
The register lists construction as complete.
Who is building Azizi Riviera 31?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 31?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.