Azizi Riviera 25 construction progress

The register lists Azizi Riviera 25 in Meydan One Community as complete, with a registered completion date of June 2023. Its last site inspection on record was in October 2023. The developer is Azizi Developments.

100%

Built, at the site inspection of 17 October 2023

Construction complete

Registered completion date
June 2023
Construction started
November 2017
First registered
March 2021
Units
276
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي ريفييرا 25
Project number
2230
Site inspections
5

Schedule

The register lists Azizi Riviera 25 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820202022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 October 2023

100%+23 pts

  • Azizi Riviera 25 construction site, inspection photo 1, 17 October 2023
  • Azizi Riviera 25 construction site, inspection photo 2, 17 October 2023
  • Azizi Riviera 25 construction site, inspection photo 3, 17 October 2023
  • Azizi Riviera 25 construction site, inspection photo 4, 17 October 2023

5 July 2022

77%+9.3 pts

  • Azizi Riviera 25 construction site, inspection photo 1, 5 July 2022
  • Azizi Riviera 25 construction site, inspection photo 2, 5 July 2022
  • Azizi Riviera 25 construction site, inspection photo 3, 5 July 2022
  • Azizi Riviera 25 construction site, inspection photo 4, 5 July 2022

28 November 2021

68%+17 pts

  • Azizi Riviera 25 construction site, inspection photo 1, 28 November 2021
  • Azizi Riviera 25 construction site, inspection photo 2, 28 November 2021
  • Azizi Riviera 25 construction site, inspection photo 3, 28 November 2021
  • Azizi Riviera 25 construction site, inspection photo 4, 28 November 2021

24 June 2021

51%+9.4 pts

  • Azizi Riviera 25 construction site, inspection photo 1, 24 June 2021
  • Azizi Riviera 25 construction site, inspection photo 2, 24 June 2021
  • Azizi Riviera 25 construction site, inspection photo 3, 24 June 2021
  • Azizi Riviera 25 construction site, inspection photo 4, 24 June 2021

18 February 2021

42%

  • Azizi Riviera 25 construction site, inspection photo 1, 18 February 2021
  • Azizi Riviera 25 construction site, inspection photo 2, 18 February 2021
  • Azizi Riviera 25 construction site, inspection photo 3, 18 February 2021
  • Azizi Riviera 25 construction site, inspection photo 4, 18 February 2021

All 50 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 25?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 25 handover date?
Construction of Azizi Riviera 25 is recorded as complete, with a registered completion date of June 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Riviera 25?
Azizi Riviera 25 was 100% built at the site inspection on 17 October 2023. The site has been inspected 5 times since February 2021. The Land Department took 50 site photos at its inspections.
Is Azizi Riviera 25 delayed?
The register lists construction as complete.
Who is building Azizi Riviera 25?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 25?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.