Azizi Riviera 24 construction progress

The register lists Azizi Riviera 24 in Meydan One Community as complete, with a registered completion date of March 2023. Its last site inspection on record was in November 2023. The developer is Azizi Developments.

100%

Built, at the site inspection of 28 November 2023

Construction complete

Registered completion date
March 2023
Construction started
December 2018
First registered
December 2018
Units
211
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي ريفيرا 24
Project number
2120
Site inspections
8

Schedule

The register lists Azizi Riviera 24 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20192020202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 November 2023

100%+23 pts

  • Azizi Riviera 24 construction site, inspection photo 1, 28 November 2023
  • Azizi Riviera 24 construction site, inspection photo 2, 28 November 2023
  • Azizi Riviera 24 construction site, inspection photo 3, 28 November 2023
  • Azizi Riviera 24 construction site, inspection photo 4, 28 November 2023

19 April 2022

77%+9.1 pts

  • Azizi Riviera 24 construction site, inspection photo 1, 19 April 2022
  • Azizi Riviera 24 construction site, inspection photo 2, 19 April 2022
  • Azizi Riviera 24 construction site, inspection photo 3, 19 April 2022
  • Azizi Riviera 24 construction site, inspection photo 4, 19 April 2022

2 November 2021

68%+20 pts

  • Azizi Riviera 24 construction site, inspection photo 1, 2 November 2021
  • Azizi Riviera 24 construction site, inspection photo 2, 2 November 2021
  • Azizi Riviera 24 construction site, inspection photo 3, 2 November 2021
  • Azizi Riviera 24 construction site, inspection photo 4, 2 November 2021

30 March 2021

48%+20 pts

  • Azizi Riviera 24 construction site, inspection photo 1, 30 March 2021
  • Azizi Riviera 24 construction site, inspection photo 2, 30 March 2021
  • Azizi Riviera 24 construction site, inspection photo 3, 30 March 2021
  • Azizi Riviera 24 construction site, inspection photo 4, 30 March 2021

7 September 2020

27%+11 pts

  • Azizi Riviera 24 construction site, inspection photo 1, 7 September 2020
  • Azizi Riviera 24 construction site, inspection photo 2, 7 September 2020
  • Azizi Riviera 24 construction site, inspection photo 3, 7 September 2020
  • Azizi Riviera 24 construction site, inspection photo 4, 7 September 2020

4 March 2020

16%+3.3 pts

  • Azizi Riviera 24 construction site, inspection photo 1, 4 March 2020
  • Azizi Riviera 24 construction site, inspection photo 2, 4 March 2020
  • Azizi Riviera 24 construction site, inspection photo 3, 4 March 2020
  • Azizi Riviera 24 construction site, inspection photo 4, 4 March 2020

26 November 2019

13%

  • Azizi Riviera 24 construction site, inspection photo 1, 26 November 2019
  • Azizi Riviera 24 construction site, inspection photo 2, 26 November 2019
  • Azizi Riviera 24 construction site, inspection photo 3, 26 November 2019
  • Azizi Riviera 24 construction site, inspection photo 4, 26 November 2019

4 September 2019

13%

  • Azizi Riviera 24 construction site, inspection photo 1, 4 September 2019
  • Azizi Riviera 24 construction site, inspection photo 2, 4 September 2019
  • Azizi Riviera 24 construction site, inspection photo 3, 4 September 2019
  • Azizi Riviera 24 construction site, inspection photo 4, 4 September 2019

All 65 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 24?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 24 handover date?
Construction of Azizi Riviera 24 is recorded as complete, with a registered completion date of March 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Riviera 24?
Azizi Riviera 24 was 100% built at the site inspection on 28 November 2023. The site has been inspected 8 times since September 2019. The Land Department took 65 site photos at its inspections.
Is Azizi Riviera 24 delayed?
The register lists construction as complete.
Who is building Azizi Riviera 24?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 24?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.