Azizi Riviera 18 construction progress

The register lists Azizi Riviera 18 in Meydan One Community as complete, with a registered completion date of July 2023. Its last site inspection on record was in July 2023. The developer is Azizi Developments.

100%

Built, at the site inspection of 14 July 2023

Construction complete

Registered completion date
July 2023
Construction started
December 2017
First registered
November 2017
Units
282
Escrow bank
Ajman Bank
Name in Arabic
عزيزي ريفيرا 18
Project number
1996
Site inspections
11

Schedule

The register lists Azizi Riviera 18 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820202022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 July 2023

100%+12 pts

  • Azizi Riviera 18 construction site, inspection photo 1, 14 July 2023
  • Azizi Riviera 18 construction site, inspection photo 2, 14 July 2023
  • Azizi Riviera 18 construction site, inspection photo 3, 14 July 2023
  • Azizi Riviera 18 construction site, inspection photo 4, 14 July 2023

1 November 2022

88%+6.2 pts

  • Azizi Riviera 18 construction site, inspection photo 1, 1 November 2022
  • Azizi Riviera 18 construction site, inspection photo 2, 1 November 2022
  • Azizi Riviera 18 construction site, inspection photo 3, 1 November 2022
  • Azizi Riviera 18 construction site, inspection photo 4, 1 November 2022

24 February 2022

82%+20 pts

  • Azizi Riviera 18 construction site, inspection photo 1, 24 February 2022
  • Azizi Riviera 18 construction site, inspection photo 2, 24 February 2022
  • Azizi Riviera 18 construction site, inspection photo 3, 24 February 2022
  • Azizi Riviera 18 construction site, inspection photo 4, 24 February 2022

5 April 2021

62%+13 pts

  • Azizi Riviera 18 construction site, inspection photo 1, 5 April 2021
  • Azizi Riviera 18 construction site, inspection photo 2, 5 April 2021
  • Azizi Riviera 18 construction site, inspection photo 3, 5 April 2021
  • Azizi Riviera 18 construction site, inspection photo 4, 5 April 2021

11 November 2020

49%+6.6 pts

  • Azizi Riviera 18 construction site, inspection photo 1, 11 November 2020
  • Azizi Riviera 18 construction site, inspection photo 2, 11 November 2020
  • Azizi Riviera 18 construction site, inspection photo 3, 11 November 2020
  • Azizi Riviera 18 construction site, inspection photo 4, 11 November 2020

14 July 2020

42%+5.0 pts

  • Azizi Riviera 18 construction site, inspection photo 1, 14 July 2020
  • Azizi Riviera 18 construction site, inspection photo 2, 14 July 2020
  • Azizi Riviera 18 construction site, inspection photo 3, 14 July 2020
  • Azizi Riviera 18 construction site, inspection photo 4, 14 July 2020

17 February 2020

37%+4.4 pts

  • Azizi Riviera 18 construction site, inspection photo 1, 17 February 2020
  • Azizi Riviera 18 construction site, inspection photo 2, 17 February 2020
  • Azizi Riviera 18 construction site, inspection photo 3, 17 February 2020
  • Azizi Riviera 18 construction site, inspection photo 4, 17 February 2020

9 December 2019

33%+12 pts

  • Azizi Riviera 18 construction site, inspection photo 1, 9 December 2019
  • Azizi Riviera 18 construction site, inspection photo 2, 9 December 2019
  • Azizi Riviera 18 construction site, inspection photo 3, 9 December 2019
  • Azizi Riviera 18 construction site, inspection photo 4, 9 December 2019

10 April 2019

21%+5.5 pts

  • Azizi Riviera 18 construction site, inspection photo 1, 10 April 2019
  • Azizi Riviera 18 construction site, inspection photo 2, 10 April 2019
  • Azizi Riviera 18 construction site, inspection photo 3, 10 April 2019
  • Azizi Riviera 18 construction site, inspection photo 4, 10 April 2019

3 January 2019

15%+5.1 pts

  • Azizi Riviera 18 construction site, inspection photo 1, 3 January 2019
  • Azizi Riviera 18 construction site, inspection photo 2, 3 January 2019
  • Azizi Riviera 18 construction site, inspection photo 3, 3 January 2019
  • Azizi Riviera 18 construction site, inspection photo 4, 3 January 2019

All 112 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 18?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 18 handover date?
Construction of Azizi Riviera 18 is recorded as complete, with a registered completion date of July 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Riviera 18?
Azizi Riviera 18 was 100% built at the site inspection on 14 July 2023. The site has been inspected 11 times since August 2018. The Land Department took 112 site photos at its inspections.
Is Azizi Riviera 18 delayed?
The register lists construction as complete.
Who is building Azizi Riviera 18?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 18?
Ajman Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.