Rijas Suites construction progress

The registered completion date for Rijas Suites in Majan is December 2028. At the last site inspection, in June 2026, it was 3.3% built. The developer is Dusit Rijas Properties.

3.3%

Built, at the site inspection of 29 June 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
April 2050
Construction started
November 2024
First registered
January 2025
Developer
Dusit Rijas Properties
Community
Majan
Units
153
Escrow bank
United Bank Limited
Name in Arabic
ريجاس سو ايتس
Project number
3433
Site inspections
3

Schedule

Between September 2025 and June 2026 the site added about 0.3 points a month. At that rate it would finish around April 2050, more than three months after its registered date of December 2028.

0%25%50%75%100%2025202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 June 2026

3.3%+3.3 pts

  • Rijas Suites construction site, inspection photo 1, 29 June 2026
  • Rijas Suites construction site, inspection photo 2, 29 June 2026

3 September 2025

0%

  • Rijas Suites construction site, inspection photo 1, 3 September 2025
  • Rijas Suites construction site, inspection photo 2, 3 September 2025

29 November 2024

0%

  • Rijas Suites construction site, inspection photo 1, 29 November 2024
  • Rijas Suites construction site, inspection photo 2, 29 November 2024

All 6 site photos, by inspection date

Context

Majan has 25 projects under construction, 28% built on average.

Own a unit in Rijas Suites?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Rijas Suites handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2050. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Rijas Suites?
Rijas Suites was 3.3% built at the site inspection on 29 June 2026. The site has been inspected 3 times since November 2024. The Land Department took 6 site photos at its inspections.
Is Rijas Suites delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Rijas Suites?
The registered developer is Dusit Rijas Properties.
Which bank holds the escrow account for Rijas Suites?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.