Rijas Suites construction progress
The registered completion date for Rijas Suites in Majan is December 2028. At the last site inspection, in June 2026, it was 3.3% built. The developer is Dusit Rijas Properties.
3.3%
Built, at the site inspection of 29 June 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- April 2050
- Construction started
- November 2024
- First registered
- January 2025
- Developer
- Dusit Rijas Properties
- Community
- Majan
- Units
- 153
- Escrow bank
- United Bank Limited
- Name in Arabic
- ريجاس سو ايتس
- Project number
- 3433
- Site inspections
- 3
Schedule
Between September 2025 and June 2026 the site added about 0.3 points a month. At that rate it would finish around April 2050, more than three months after its registered date of December 2028.
Site inspections
29 June 2026
3.3%+3.3 pts
3 September 2025
0%
29 November 2024
0%
Context
Majan has 25 projects under construction, 28% built on average.
Own a unit in Rijas Suites?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Rijas Suites handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2050. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Rijas Suites?
- Rijas Suites was 3.3% built at the site inspection on 29 June 2026. The site has been inspected 3 times since November 2024. The Land Department took 6 site photos at its inspections.
- Is Rijas Suites delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Rijas Suites?
- The registered developer is Dusit Rijas Properties.
- Which bank holds the escrow account for Rijas Suites?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sherena Residence 2Nearby in Majan. 82%, Due August 2022, passed.
- Samana Barari ViewsNearby in Majan. 32%, Due March 2027.
- Samana Barari Views 2Nearby in Majan. 26%.
- Barari Parkview By Al MawaredNearby in Majan. 45%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.