Rijas Suites in Majan is 3.3% built at the Land Department inspection of June 2026. Developer Dusit Rijas Properties. Completion registered for December 2028.
3.3%
Built, at the Land Department site inspection of 29 June 2026
Running behind its date
- Completion date (Land Department)
- December 2028
- Finish at recent pace
- April 2050
- Construction started
- November 2024
- Registered with the Land Department
- January 2025
- Developer
- Dusit Rijas Properties
- Community
- Majan
- Units
- 153
- Escrow bank
- United Bank Limited
- Name in Arabic
- ريجاس سو ايتس
- Land Department project number
- 3433
- Land Department site inspections
- 3
Schedule
Between September 2025 and June 2026 the site added about 0.3 points a month. At that rate it would finish around April 2050, more than three months after the December 2028 date registered with the Land Department.
Site inspections
29 June 2026
3.3%+3.3 pts
3 September 2025
0%
29 November 2024
0%
Context
Majan has 25 projects under construction, 24% built on average.
Own a unit in Rijas Suites?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Rijas Suites be completed?
- The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around April 2050. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Rijas Suites is built?
- 3.3%, measured at the Land Department site inspection on 29 June 2026. The Land Department engineers have inspected the site 3 times since November 2024.
- Is Rijas Suites delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Rijas Suites?
- The registered developer is Dusit Rijas Properties.
- Which bank holds the escrow account for Rijas Suites?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sherena Residence 2Nearby in Majan. 82%, Due August 2022, passed.
- Samana Barari ViewsNearby in Majan. 27%, Due March 2027.
- Samana Barari Views 2Nearby in Majan. 20%.
- Barari Parkview By Al MawaredNearby in Majan. 45%, Due December 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.