Mangrove 2 construction progress

Mangrove 2 in Majan is 38% built at the Land Department inspection of August 2026. Developer Mangrove Real Estate Development. Completion registered for September 2026.

38%

Built, at the Land Department site inspection of 10 August 2026

1 months past its registered completion date

Completion date (Land Department)
September 2026
Finish at recent pace
December 2027
Construction started
May 2025
Registered with the Land Department
July 2025
Developer
Mangrove Real Estate Development
Community
Majan
Units
18
Escrow bank
Arab Bank
Name in Arabic
مانجروف 2
Land Department project number
3597
Land Department site inspections
3

Schedule

Mangrove 2 was registered to complete in September 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 3.7 points a month. Kept at that rate, the site would reach 100% around December 2027.

0%25%50%75%100%2026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

10 August 2026

38%+25 pts

  • Mangrove 2 construction site, Land Department inspection photo 1, 10 August 2026
  • Mangrove 2 construction site, Land Department inspection photo 2, 10 August 2026
  • Mangrove 2 construction site, Land Department inspection photo 3, 10 August 2026
  • Mangrove 2 construction site, Land Department inspection photo 4, 10 August 2026

19 January 2026

13%+13 pts

  • Mangrove 2 construction site, Land Department inspection photo 1, 19 January 2026
  • Mangrove 2 construction site, Land Department inspection photo 2, 19 January 2026
  • Mangrove 2 construction site, Land Department inspection photo 3, 19 January 2026
  • Mangrove 2 construction site, Land Department inspection photo 4, 19 January 2026

3 July 2025

0%

  • Mangrove 2 construction site, Land Department inspection photo 1, 3 July 2025
  • Mangrove 2 construction site, Land Department inspection photo 2, 3 July 2025

All 19 site photos, by inspection date

Context

Majan has 25 projects under construction, 24% built on average. Mangrove 2 is ahead of that average.

Own a unit in Mangrove 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Mangrove 2 be completed?
The completion date registered with the Dubai Land Department is September 2026. At the pace of its recent inspections the site would reach 100% around December 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Mangrove 2 is built?
38%, measured at the Land Department site inspection on 10 August 2026. The Land Department engineers have inspected the site 3 times since July 2025.
Is Mangrove 2 delayed?
Yes. Its registered completion date of September 2026 has passed and the Land Department still lists it as under construction.
Who is building Mangrove 2?
The registered developer is Mangrove Real Estate Development.
Which bank holds the escrow account for Mangrove 2?
Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.