Mangrove 2 construction progress
Mangrove 2 in Majan was registered to complete in September 2026 and is still under construction. At the last site inspection, in August 2026, it was 38% built. The developer is Mangrove Real Estate Development.
38%
Built, at the site inspection of 10 August 2026
2 months past its registered completion date
- Registered completion date
- September 2026
- Finish at recent pace
- December 2027
- Construction started
- May 2025
- First registered
- July 2025
- Developer
- Mangrove Real Estate Development
- Community
- Majan
- Units
- 18
- Escrow bank
- Arab Bank
- Name in Arabic
- مانجروف 2
- Project number
- 3597
- Site inspections
- 3
Schedule
Mangrove 2 was registered to complete in September 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 3.7 points a month. Kept at that rate, the site would reach 100% around December 2027.
Site inspections
10 August 2026
38%+25 pts
19 January 2026
13%+13 pts
3 July 2025
0%
Context
Majan has 25 projects under construction, 28% built on average.
Own a unit in Mangrove 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Mangrove 2 handover date?
- The registered completion date was September 2026, and the register still lists Mangrove 2 as under construction. At the pace of its recent inspections the site would reach 100% around December 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Mangrove 2?
- Mangrove 2 was 38% built at the site inspection on 10 August 2026. The site has been inspected 3 times since July 2025. The Land Department took 19 site photos at its inspections.
- Is Mangrove 2 delayed?
- Yes. Its registered completion date of September 2026 has passed and the project is still listed as under construction.
- Who is building Mangrove 2?
- The registered developer is Mangrove Real Estate Development.
- Which bank holds the escrow account for Mangrove 2?
- Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sherena Residence 2Nearby in Majan. 82%, Due August 2022, passed.
- Samana Barari ViewsNearby in Majan. 32%, Due March 2027.
- Samana Barari Views 2Nearby in Majan. 26%.
- Barari Parkview By Al MawaredNearby in Majan. 45%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.