Lazord By Lapis construction progress
The registered completion date for Lazord By Lapis in Majan is December 2026. At the last site inspection, in September 2026, it was 28% built. The developer is Lapis Properties.
28%
Built, at the site inspection of 3 September 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- June 2029
- Construction started
- January 2025
- First registered
- September 2024
- Developer
- Lapis Properties
- Community
- Majan
- Units
- 313
- Escrow bank
- Mashreq Bank
- Name in Arabic
- لازورد باي لابيس
- Project number
- 3209
- Site inspections
- 6
Schedule
Between September 2025 and September 2026 the site added about 2.1 points a month. At that rate it would finish around June 2029, more than three months after its registered date of December 2026.
Site inspections
3 September 2026
28%+15 pts
30 April 2026
13%+5.1 pts
9 February 2026
8.0%+5.6 pts
8 September 2025
2.4%+2.2 pts
8 May 2025
0.2%+0.2 pts
31 July 2024
0%
Context
Majan has 25 projects under construction, 28% built on average.
Own a unit in Lazord By Lapis?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Lazord By Lapis handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Lazord By Lapis?
- Lazord By Lapis was 28% built at the site inspection on 3 September 2026. The site has been inspected 6 times since July 2024. The Land Department took 27 site photos at its inspections.
- Is Lazord By Lapis delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Lazord By Lapis?
- The registered developer is Lapis Properties.
- Which bank holds the escrow account for Lazord By Lapis?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sherena Residence 2Nearby in Majan. 82%, Due August 2022, passed.
- Samana Barari ViewsNearby in Majan. 32%, Due March 2027.
- Samana Barari Views 2Nearby in Majan. 26%.
- Barari Parkview By Al MawaredNearby in Majan. 45%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

