Lazord By Lapis construction progress

The registered completion date for Lazord By Lapis in Majan is December 2026. At the last site inspection, in September 2026, it was 28% built. The developer is Lapis Properties.

28%

Built, at the site inspection of 3 September 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
June 2029
Construction started
January 2025
First registered
September 2024
Developer
Lapis Properties
Community
Majan
Units
313
Escrow bank
Mashreq Bank
Name in Arabic
لازورد باي لابيس
Project number
3209
Site inspections
6

Schedule

Between September 2025 and September 2026 the site added about 2.1 points a month. At that rate it would finish around June 2029, more than three months after its registered date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 September 2026

28%+15 pts

  • Lazord By Lapis construction site, inspection photo 1, 3 September 2026
  • Lazord By Lapis construction site, inspection photo 2, 3 September 2026
  • Lazord By Lapis construction site, inspection photo 3, 3 September 2026
  • Lazord By Lapis construction site, inspection photo 4, 3 September 2026

30 April 2026

13%+5.1 pts

  • Lazord By Lapis construction site, inspection photo 1, 30 April 2026
  • Lazord By Lapis construction site, inspection photo 2, 30 April 2026
  • Lazord By Lapis construction site, inspection photo 3, 30 April 2026
  • Lazord By Lapis construction site, inspection photo 4, 30 April 2026

9 February 2026

8.0%+5.6 pts

  • Lazord By Lapis construction site, inspection photo 1, 9 February 2026
  • Lazord By Lapis construction site, inspection photo 2, 9 February 2026
  • Lazord By Lapis construction site, inspection photo 3, 9 February 2026
  • Lazord By Lapis construction site, inspection photo 4, 9 February 2026

8 September 2025

2.4%+2.2 pts

  • Lazord By Lapis construction site, inspection photo 1, 8 September 2025
  • Lazord By Lapis construction site, inspection photo 2, 8 September 2025
  • Lazord By Lapis construction site, inspection photo 3, 8 September 2025
  • Lazord By Lapis construction site, inspection photo 4, 8 September 2025

8 May 2025

0.2%+0.2 pts

  • Lazord By Lapis construction site, inspection photo 1, 8 May 2025
  • Lazord By Lapis construction site, inspection photo 2, 8 May 2025
  • Lazord By Lapis construction site, inspection photo 3, 8 May 2025
  • Lazord By Lapis construction site, inspection photo 4, 8 May 2025

31 July 2024

0%

  • Lazord By Lapis construction site, inspection photo 1, 31 July 2024
  • Lazord By Lapis construction site, inspection photo 2, 31 July 2024

All 27 site photos, by inspection date

Context

Majan has 25 projects under construction, 28% built on average.

Own a unit in Lazord By Lapis?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Lazord By Lapis handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Lazord By Lapis?
Lazord By Lapis was 28% built at the site inspection on 3 September 2026. The site has been inspected 6 times since July 2024. The Land Department took 27 site photos at its inspections.
Is Lazord By Lapis delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Lazord By Lapis?
The registered developer is Lapis Properties.
Which bank holds the escrow account for Lazord By Lapis?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.