Iliyaa 5 construction progress

The register lists Iliyaa 5 in Majan as complete, with a registered completion date of April 2025. Its last site inspection on record was in October 2025. The developer is Illyaa Real Estate Development.

100%

Built, at the site inspection of 17 October 2025

Construction complete

Registered completion date
April 2025
Construction started
July 2023
First registered
September 2024
Developer
Illyaa Real Estate Development
Community
Majan
Units
100
Escrow bank
United Arab Bank
Name in Arabic
ايلياء 5
Project number
3013
Site inspections
3

Schedule

The register lists Iliyaa 5 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 October 2025

100%+5.0 pts

  • Iliyaa 5 construction site, inspection photo 1, 17 October 2025
  • Iliyaa 5 construction site, inspection photo 2, 17 October 2025
  • Iliyaa 5 construction site, inspection photo 3, 17 October 2025
  • Iliyaa 5 construction site, inspection photo 4, 17 October 2025

30 May 2025

95%+63 pts

  • Iliyaa 5 construction site, inspection photo 1, 30 May 2025
  • Iliyaa 5 construction site, inspection photo 2, 30 May 2025
  • Iliyaa 5 construction site, inspection photo 3, 30 May 2025
  • Iliyaa 5 construction site, inspection photo 4, 30 May 2025

11 July 2024

32%

  • Iliyaa 5 construction site, inspection photo 1, 11 July 2024
  • Iliyaa 5 construction site, inspection photo 2, 11 July 2024
  • Iliyaa 5 construction site, inspection photo 3, 11 July 2024

All 29 site photos, by inspection date

Context

Majan has 25 projects under construction, 28% built on average.

Own a unit in Iliyaa 5?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Iliyaa 5 handover date?
Construction of Iliyaa 5 is recorded as complete, with a registered completion date of April 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Iliyaa 5?
Iliyaa 5 was 100% built at the site inspection on 17 October 2025. The site has been inspected 3 times since July 2024. The Land Department took 29 site photos at its inspections.
Is Iliyaa 5 delayed?
The register lists construction as complete.
Who is building Iliyaa 5?
The registered developer is Illyaa Real Estate Development.
Which bank holds the escrow account for Iliyaa 5?
United Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.