Estrella By Nexus construction progress
Estrella By Nexus in Majan was registered to complete in May 2026 and is still under construction. At the last site inspection, in May 2026, it was 46% built. The developer is Nexus Capital Real Estate Developement.
46%
Built, at the site inspection of 21 May 2026
6 months past its registered completion date
- Registered completion date
- May 2026
- Finish at recent pace
- October 2027
- Construction started
- July 2024
- First registered
- February 2025
- Developer
- Nexus Capital Real Estate Developement
- Community
- Majan
- Units
- 60
- Escrow bank
- United Bank Limited
- Name in Arabic
- استريلا من نكسيس
- Project number
- 3284
- Site inspections
- 4
Schedule
Estrella By Nexus was registered to complete in May 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 3.2 points a month. Kept at that rate, the site would reach 100% around October 2027.
Site inspections
21 May 2026
46%+7.0 pts
5 February 2026
39%+23 pts
4 August 2025
15%+11 pts
16 October 2024
3.9%
Context
Majan has 25 projects under construction, 28% built on average.
Own a unit in Estrella By Nexus?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Estrella By Nexus handover date?
- The registered completion date was May 2026, and the register still lists Estrella By Nexus as under construction. At the pace of its recent inspections the site would reach 100% around October 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Estrella By Nexus?
- Estrella By Nexus was 46% built at the site inspection on 21 May 2026. The site has been inspected 4 times since October 2024. The Land Department took 27 site photos at its inspections.
- Is Estrella By Nexus delayed?
- Yes. Its registered completion date of May 2026 has passed and the project is still listed as under construction.
- Who is building Estrella By Nexus?
- The registered developer is Nexus Capital Real Estate Developement.
- Which bank holds the escrow account for Estrella By Nexus?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sherena Residence 2Nearby in Majan. 82%, Due August 2022, passed.
- Samana Barari ViewsNearby in Majan. 32%, Due March 2027.
- Samana Barari Views 2Nearby in Majan. 26%.
- Barari Parkview By Al MawaredNearby in Majan. 45%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)








.jpeg&w=3840&q=75)