Aras Residence construction progress

The register lists Aras Residence in Majan as complete, with a registered completion date of June 2022. Its last site inspection on record was in August 2022. The developer is A R A S Real Estate Development.

100%

Built, at the site inspection of 31 August 2022

Construction complete

Registered completion date
June 2022
Construction started
February 2020
First registered
May 2021
Developer
A R A S Real Estate Development
Community
Majan
Units
96
Escrow bank
Emirates NBD
Name in Arabic
أراس ريزيدنس
Project number
2235
Site inspections
5

Schedule

The register lists Aras Residence as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

31 August 2022

100%+3.2 pts

  • Aras Residence construction site, inspection photo 1, 31 August 2022
  • Aras Residence construction site, inspection photo 2, 31 August 2022
  • Aras Residence construction site, inspection photo 3, 31 August 2022
  • Aras Residence construction site, inspection photo 4, 31 August 2022

7 July 2022

97%+14 pts

  • Aras Residence construction site, inspection photo 1, 7 July 2022
  • Aras Residence construction site, inspection photo 2, 7 July 2022
  • Aras Residence construction site, inspection photo 3, 7 July 2022
  • Aras Residence construction site, inspection photo 4, 7 July 2022

31 January 2022

82%+22 pts

  • Aras Residence construction site, inspection photo 1, 31 January 2022
  • Aras Residence construction site, inspection photo 2, 31 January 2022
  • Aras Residence construction site, inspection photo 3, 31 January 2022
  • Aras Residence construction site, inspection photo 4, 31 January 2022

12 July 2021

61%+17 pts

  • Aras Residence construction site, inspection photo 1, 12 July 2021
  • Aras Residence construction site, inspection photo 2, 12 July 2021
  • Aras Residence construction site, inspection photo 3, 12 July 2021
  • Aras Residence construction site, inspection photo 4, 12 July 2021

8 March 2021

44%

  • Aras Residence construction site, inspection photo 1, 8 March 2021
  • Aras Residence construction site, inspection photo 2, 8 March 2021
  • Aras Residence construction site, inspection photo 3, 8 March 2021
  • Aras Residence construction site, inspection photo 4, 8 March 2021

All 57 site photos, by inspection date

Context

Majan has 25 projects under construction, 28% built on average.

Own a unit in Aras Residence?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Aras Residence handover date?
Construction of Aras Residence is recorded as complete, with a registered completion date of June 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Aras Residence?
Aras Residence was 100% built at the site inspection on 31 August 2022. The site has been inspected 5 times since March 2021. The Land Department took 57 site photos at its inspections.
Is Aras Residence delayed?
The register lists construction as complete.
Who is building Aras Residence?
The registered developer is A R A S Real Estate Development.
Which bank holds the escrow account for Aras Residence?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.