Skip to content

Amethyst By Siroya construction progress

The register lists Amethyst By Siroya in Majan as complete, with a registered completion date of November 2025. Its last site inspection on record was in July 2026. The developer is Siroya Ventures Realty.

100%

Built, at the site inspection of 13 July 2026

Construction complete

Registered completion date
November 2025
Construction started
August 2024
First registered
November 2024
Developer
Siroya Ventures Realty
Community
Majan
Units
53
Escrow bank
Bank of Baroda
Name in Arabic
اميثيست بواسطة سيرويا
Project number
3244
Site inspections
5

Schedule

The register lists Amethyst By Siroya as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 July 2026

100%+4.0 pts

  • Amethyst By Siroya construction site, inspection photo 1, 13 July 2026
  • Amethyst By Siroya construction site, inspection photo 2, 13 July 2026
  • Amethyst By Siroya construction site, inspection photo 3, 13 July 2026
  • Amethyst By Siroya construction site, inspection photo 4, 13 July 2026

8 May 2026

96%+56 pts

  • Amethyst By Siroya construction site, inspection photo 1, 8 May 2026
  • Amethyst By Siroya construction site, inspection photo 2, 8 May 2026
  • Amethyst By Siroya construction site, inspection photo 3, 8 May 2026
  • Amethyst By Siroya construction site, inspection photo 4, 8 May 2026

23 May 2025

40%+7.6 pts

  • Amethyst By Siroya construction site, inspection photo 1, 23 May 2025
  • Amethyst By Siroya construction site, inspection photo 2, 23 May 2025
  • Amethyst By Siroya construction site, inspection photo 3, 23 May 2025
  • Amethyst By Siroya construction site, inspection photo 4, 23 May 2025

3 March 2025

33%+33 pts

  • Amethyst By Siroya construction site, inspection photo 1, 3 March 2025
  • Amethyst By Siroya construction site, inspection photo 2, 3 March 2025
  • Amethyst By Siroya construction site, inspection photo 3, 3 March 2025
  • Amethyst By Siroya construction site, inspection photo 4, 3 March 2025

19 September 2024

0%

  • Amethyst By Siroya construction site, inspection photo 1, 19 September 2024
  • Amethyst By Siroya construction site, inspection photo 2, 19 September 2024

All 37 site photos, by inspection date

Context

Majan has 25 projects under construction, 28% built on average.

Own a unit in Amethyst By Siroya?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Amethyst By Siroya handover date?
Construction of Amethyst By Siroya is recorded as complete, with a registered completion date of November 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Amethyst By Siroya?
Amethyst By Siroya was 100% built at the site inspection on 13 July 2026. The site has been inspected 5 times since September 2024. The Land Department took 37 site photos at its inspections.
Is Amethyst By Siroya delayed?
The register lists construction as complete.
Who is building Amethyst By Siroya?
The registered developer is Siroya Ventures Realty.
Which bank holds the escrow account for Amethyst By Siroya?
Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.