Maya Townhouses construction progress

The register lists Maya Townhouses in Living Legends as complete, with a registered completion date of July 2023. Its last site inspection on record was in February 2024. The developer is Al Andalus Court Yard Real Estate Development.

100%

Built, at the site inspection of 28 February 2024

Construction complete

Registered completion date
July 2023
Construction started
May 2022
First registered
March 2023
Developer
Al Andalus Court Yard Real Estate Development
Units
30
Escrow bank
Emirates NBD
Name in Arabic
مايا تاون هاوس
Project number
2453
Site inspections
5

Schedule

The register lists Maya Townhouses as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 February 2024

100%+4.7 pts

  • Maya Townhouses construction site, inspection photo 1, 28 February 2024
  • Maya Townhouses construction site, inspection photo 2, 28 February 2024
  • Maya Townhouses construction site, inspection photo 3, 28 February 2024
  • Maya Townhouses construction site, inspection photo 4, 28 February 2024

20 September 2023

95%+14 pts

  • Maya Townhouses construction site, inspection photo 1, 20 September 2023
  • Maya Townhouses construction site, inspection photo 2, 20 September 2023
  • Maya Townhouses construction site, inspection photo 3, 20 September 2023
  • Maya Townhouses construction site, inspection photo 4, 20 September 2023

19 April 2023

81%+31 pts

  • Maya Townhouses construction site, inspection photo 1, 19 April 2023
  • Maya Townhouses construction site, inspection photo 2, 19 April 2023
  • Maya Townhouses construction site, inspection photo 3, 19 April 2023
  • Maya Townhouses construction site, inspection photo 4, 19 April 2023

28 November 2022

50%+22 pts

  • Maya Townhouses construction site, inspection photo 1, 28 November 2022
  • Maya Townhouses construction site, inspection photo 2, 28 November 2022
  • Maya Townhouses construction site, inspection photo 3, 28 November 2022
  • Maya Townhouses construction site, inspection photo 4, 28 November 2022

26 September 2022

29%

  • Maya Townhouses construction site, inspection photo 1, 26 September 2022
  • Maya Townhouses construction site, inspection photo 2, 26 September 2022
  • Maya Townhouses construction site, inspection photo 3, 26 September 2022
  • Maya Townhouses construction site, inspection photo 4, 26 September 2022

All 49 site photos, by inspection date

Context

Living Legends has 6 projects under construction, 49% built on average.

Own a unit in Maya Townhouses?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Maya Townhouses handover date?
Construction of Maya Townhouses is recorded as complete, with a registered completion date of July 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Maya Townhouses?
Maya Townhouses was 100% built at the site inspection on 28 February 2024. The site has been inspected 5 times since September 2022. The Land Department took 49 site photos at its inspections.
Is Maya Townhouses delayed?
The register lists construction as complete.
Who is building Maya Townhouses?
The registered developer is Al Andalus Court Yard Real Estate Development.
Which bank holds the escrow account for Maya Townhouses?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.