188 photos from 19 site inspections, newest first. The percentage is how much of Living Legends Phase 7 was built on the day of each visit.

27 January 202292% built

2 August 202192% built

9 February 202192% built

15 October 202091% built

8 May 201988% built

11 December 201882% built

29 July 201880% built

18 February 201871% built

12 September 201768% built

21 November 201667% built

28 June 201664% built

28 September 201560% built

6 April 201551% built

9 December 201447% built

23 September 201433% built

11 March 201422% built

31 October 201315% built

20 May 201313% built

4 November 20125.7% built

Back to Living Legends Phase 7 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.