Living Legends Phase 1 construction progress
The register lists Living Legends Phase 1 in Living Legends as complete, with a registered completion date of December 2015. Its last site inspection on record was in March 2017. The developer is Tanmiyat Global Real Estate Development.
100%
Built, at the site inspection of 13 March 2017
Construction complete
- Registered completion date
- December 2015
- Construction started
- August 2011
- First registered
- November 2008
- Developer
- Tanmiyat Global Real Estate Development
- Community
- Living Legends
- Units
- 147
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- ليفنج ليجند فيس ون
- Project number
- 489
- Site inspections
- 11
Schedule
The register lists Living Legends Phase 1 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
13 March 2017
100%+1.7 pts
21 June 2016
98%+0.9 pts
7 October 2015
97%+5.2 pts
5 February 2015
92%+22 pts
30 June 2014
71%+4.7 pts
9 March 2014
66%+7.7 pts
8 December 2013
58%+7.8 pts
19 August 2013
50%+7.6 pts
4 February 2013
43%+3.0 pts
24 October 2012
40%+15 pts
Context
Living Legends has 6 projects under construction, 49% built on average.
Tanmiyat Global Real Estate Development has 1 project under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Living Legends Phase 1?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Living Legends Phase 1 handover date?
- Construction of Living Legends Phase 1 is recorded as complete, with a registered completion date of December 2015. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Living Legends Phase 1?
- Living Legends Phase 1 was 100% built at the site inspection on 13 March 2017. The site has been inspected 11 times since June 2012. The Land Department took 80 site photos at its inspections.
- Is Living Legends Phase 1 delayed?
- The register lists construction as complete.
- Who is building Living Legends Phase 1?
- The registered developer is Tanmiyat Global Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Living Legends Phase 1?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Living Legends Phase 7Also by Tanmiyat Global Real Estate Development. 92%, Due September 2021, passed.
- Living Legends Phase 4Nearby in Living Legends. 62%, Due March 2027.
- Living Legends Phase 5Nearby in Living Legends. 49%, Due March 2025, passed.
- Living Legends Phase 6Nearby in Living Legends. 77%, Due July 2026, passed.
- The Wilds 1Nearby in Living Legends. 7.5%, Due January 2029.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.