Jumeirah Asora Bay construction progress

The registered completion date for Jumeirah Asora Bay in La Mer is March 2029. At the last site inspection, in August 2026, it was 4.4% built. The developer is Dhre 2 Bts.

4.4%

Built, at the site inspection of 12 August 2026

Running behind its date

Registered completion date
March 2029
Finish at recent pace
January 2049
Construction started
May 2025
First registered
February 2025
Developer
Dhre 2 Bts
Community
La Mer
Units
30
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
جميرا أسورا باي
Project number
3445
Site inspections
6

Schedule

Between August 2025 and August 2026 the site added about 0.4 points a month. At that rate it would finish around January 2049, more than three months after its registered date of March 2029.

0%25%50%75%100%20252026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 August 2026

4.4%+0.4 pts

  • Jumeirah Asora Bay construction site, inspection photo 1, 12 August 2026
  • Jumeirah Asora Bay construction site, inspection photo 2, 12 August 2026
  • Jumeirah Asora Bay construction site, inspection photo 3, 12 August 2026
  • Jumeirah Asora Bay construction site, inspection photo 4, 12 August 2026

21 May 2026

4.0%

  • Jumeirah Asora Bay construction site, inspection photo 1, 21 May 2026
  • Jumeirah Asora Bay construction site, inspection photo 2, 21 May 2026
  • Jumeirah Asora Bay construction site, inspection photo 3, 21 May 2026
  • Jumeirah Asora Bay construction site, inspection photo 4, 21 May 2026

23 February 2026

4.0%+3.4 pts

  • Jumeirah Asora Bay construction site, inspection photo 1, 23 February 2026
  • Jumeirah Asora Bay construction site, inspection photo 2, 23 February 2026
  • Jumeirah Asora Bay construction site, inspection photo 3, 23 February 2026
  • Jumeirah Asora Bay construction site, inspection photo 4, 23 February 2026

14 November 2025

0.6%+0.4 pts

  • Jumeirah Asora Bay construction site, inspection photo 1, 14 November 2025
  • Jumeirah Asora Bay construction site, inspection photo 2, 14 November 2025
  • Jumeirah Asora Bay construction site, inspection photo 3, 14 November 2025

18 August 2025

0.2%+0.2 pts

  • Jumeirah Asora Bay construction site, inspection photo 1, 18 August 2025
  • Jumeirah Asora Bay construction site, inspection photo 2, 18 August 2025
  • Jumeirah Asora Bay construction site, inspection photo 3, 18 August 2025
  • Jumeirah Asora Bay construction site, inspection photo 4, 18 August 2025

19 December 2024

0%

  • Jumeirah Asora Bay construction site, inspection photo 1, 19 December 2024
  • Jumeirah Asora Bay construction site, inspection photo 2, 19 December 2024

All 23 site photos, by inspection date

Context

La Mer has 5 projects under construction, 1.0% built on average.

Dhre 2 Bts has 12 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Jumeirah Asora Bay?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Jumeirah Asora Bay handover date?
The registered completion date is March 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2049. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Jumeirah Asora Bay?
Jumeirah Asora Bay was 4.4% built at the site inspection on 12 August 2026. The site has been inspected 6 times since December 2024. The Land Department took 23 site photos at its inspections.
Is Jumeirah Asora Bay delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2029.
Who is building Jumeirah Asora Bay?
The registered developer is Dhre 2 Bts. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Jumeirah Asora Bay?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.