Jumeirah Asora Bay construction progress

Jumeirah Asora Bay in La Mer is 4.4% built at the Land Department inspection of August 2026. Developer Dhre 2 Bts. Completion registered for March 2029.

4.4%

Built, at the Land Department site inspection of 12 August 2026

Running behind its date

Completion date (Land Department)
March 2029
Finish at recent pace
January 2049
Construction started
May 2025
Registered with the Land Department
February 2025
Developer
Dhre 2 Bts
Community
La Mer
Units
30
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
جميرا أسورا باي
Land Department project number
3445
Land Department site inspections
6

Schedule

Between August 2025 and August 2026 the site added about 0.4 points a month. At that rate it would finish around January 2049, more than three months after the March 2029 date registered with the Land Department.

0%25%50%75%100%20252026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

12 August 2026

4.4%+0.4 pts

  • Jumeirah Asora Bay construction site, Land Department inspection photo 1, 12 August 2026
  • Jumeirah Asora Bay construction site, Land Department inspection photo 2, 12 August 2026
  • Jumeirah Asora Bay construction site, Land Department inspection photo 3, 12 August 2026
  • Jumeirah Asora Bay construction site, Land Department inspection photo 4, 12 August 2026

21 May 2026

4.0%

  • Jumeirah Asora Bay construction site, Land Department inspection photo 1, 21 May 2026
  • Jumeirah Asora Bay construction site, Land Department inspection photo 2, 21 May 2026
  • Jumeirah Asora Bay construction site, Land Department inspection photo 3, 21 May 2026
  • Jumeirah Asora Bay construction site, Land Department inspection photo 4, 21 May 2026

23 February 2026

4.0%+3.4 pts

  • Jumeirah Asora Bay construction site, Land Department inspection photo 1, 23 February 2026
  • Jumeirah Asora Bay construction site, Land Department inspection photo 2, 23 February 2026
  • Jumeirah Asora Bay construction site, Land Department inspection photo 3, 23 February 2026
  • Jumeirah Asora Bay construction site, Land Department inspection photo 4, 23 February 2026

14 November 2025

0.6%+0.4 pts

  • Jumeirah Asora Bay construction site, Land Department inspection photo 1, 14 November 2025
  • Jumeirah Asora Bay construction site, Land Department inspection photo 2, 14 November 2025
  • Jumeirah Asora Bay construction site, Land Department inspection photo 3, 14 November 2025

18 August 2025

0.2%+0.2 pts

  • Jumeirah Asora Bay construction site, Land Department inspection photo 1, 18 August 2025
  • Jumeirah Asora Bay construction site, Land Department inspection photo 2, 18 August 2025
  • Jumeirah Asora Bay construction site, Land Department inspection photo 3, 18 August 2025
  • Jumeirah Asora Bay construction site, Land Department inspection photo 4, 18 August 2025

19 December 2024

0%

  • Jumeirah Asora Bay construction site, Land Department inspection photo 1, 19 December 2024
  • Jumeirah Asora Bay construction site, Land Department inspection photo 2, 19 December 2024

All 23 site photos, by inspection date

Context

La Mer has 5 projects under construction, 1.0% built on average.

Dhre 2 Bts has 11 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Jumeirah Asora Bay?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Jumeirah Asora Bay be completed?
The completion date registered with the Dubai Land Department is March 2029. At the pace of its recent inspections the site would reach 100% around January 2049. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Jumeirah Asora Bay is built?
4.4%, measured at the Land Department site inspection on 12 August 2026. The Land Department engineers have inspected the site 6 times since December 2024.
Is Jumeirah Asora Bay delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2029.
Who is building Jumeirah Asora Bay?
The registered developer is Dhre 2 Bts. It has 10 other projects under construction in Dubai.
Which bank holds the escrow account for Jumeirah Asora Bay?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.