The Vyne Residences construction progress
The Vyne Residences in Jumeirah Village Triangle is 80% built at the Land Department inspection of April 2026. Developer Metrical Real Estate Development. Completion registered for November 2026.
80%
Built, at the Land Department site inspection of 22 April 2026
On pace for its date
- Completion date (Land Department)
- November 2026
- Finish at recent pace
- August 2026
- Construction started
- May 2024
- Registered with the Land Department
- August 2024
- Developer
- Metrical Real Estate Development
- Community
- Jumeirah Village Triangle
- Units
- 263
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ذا فاين ريزدينسز
- Land Department project number
- 3094
- Land Department site inspections
- 5
Schedule
Since July 2025 The Vyne Residences has added about 4.6 points a month. That puts 100% around August 2026, within three months of its registered completion date of November 2026.
Site inspections
22 April 2026
80%+17 pts
17 December 2025
64%+27 pts
8 July 2025
37%+24 pts
25 December 2024
12%+12 pts
6 June 2024
0%
Context
Jumeirah Village Triangle has 31 projects under construction, 28% built on average.
Metrical Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Vyne Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Vyne Residences be completed?
- The completion date registered with the Dubai Land Department is November 2026. At the pace of its recent inspections the site would reach 100% around August 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Vyne Residences is built?
- 80%, measured at the Land Department site inspection on 22 April 2026. The Land Department engineers have inspected the site 5 times since June 2024.
- Is The Vyne Residences delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of November 2026.
- Who is building The Vyne Residences?
- The registered developer is Metrical Real Estate Development. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for The Vyne Residences?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Leven ResidencesAlso by Metrical Real Estate Development. 23%, Due November 2027.
- S'Vn ResidencesAlso by Metrical Real Estate Development. 0%.
- Paradise OneNearby in Jumeirah Village Triangle. 70%, Due April 2027.
- Silver StallionsNearby in Jumeirah Village Triangle. 12%, Due December 2017, passed.
- Altai TowerNearby in Jumeirah Village Triangle. 98%, Due January 2026, passed.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)