The Vyne Residences construction progress

The Vyne Residences in Jumeirah Village Triangle is 80% built at the Land Department inspection of April 2026. Developer Metrical Real Estate Development. Completion registered for November 2026.

80%

Built, at the Land Department site inspection of 22 April 2026

On pace for its date

Completion date (Land Department)
November 2026
Finish at recent pace
August 2026
Construction started
May 2024
Registered with the Land Department
August 2024
Units
263
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ذا فاين ريزدينسز
Land Department project number
3094
Land Department site inspections
5

Schedule

Since July 2025 The Vyne Residences has added about 4.6 points a month. That puts 100% around August 2026, within three months of its registered completion date of November 2026.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

22 April 2026

80%+17 pts

  • The Vyne Residences construction site, Land Department inspection photo 1, 22 April 2026
  • The Vyne Residences construction site, Land Department inspection photo 2, 22 April 2026
  • The Vyne Residences construction site, Land Department inspection photo 3, 22 April 2026
  • The Vyne Residences construction site, Land Department inspection photo 4, 22 April 2026

17 December 2025

64%+27 pts

  • The Vyne Residences construction site, Land Department inspection photo 1, 17 December 2025
  • The Vyne Residences construction site, Land Department inspection photo 2, 17 December 2025
  • The Vyne Residences construction site, Land Department inspection photo 3, 17 December 2025
  • The Vyne Residences construction site, Land Department inspection photo 4, 17 December 2025

8 July 2025

37%+24 pts

  • The Vyne Residences construction site, Land Department inspection photo 1, 8 July 2025
  • The Vyne Residences construction site, Land Department inspection photo 2, 8 July 2025
  • The Vyne Residences construction site, Land Department inspection photo 3, 8 July 2025
  • The Vyne Residences construction site, Land Department inspection photo 4, 8 July 2025

25 December 2024

12%+12 pts

  • The Vyne Residences construction site, Land Department inspection photo 1, 25 December 2024
  • The Vyne Residences construction site, Land Department inspection photo 2, 25 December 2024
  • The Vyne Residences construction site, Land Department inspection photo 3, 25 December 2024
  • The Vyne Residences construction site, Land Department inspection photo 4, 25 December 2024

6 June 2024

0%

  • The Vyne Residences construction site, Land Department inspection photo 1, 6 June 2024
  • The Vyne Residences construction site, Land Department inspection photo 2, 6 June 2024

All 32 site photos, by inspection date

Context

Jumeirah Village Triangle has 31 projects under construction, 28% built on average.

Metrical Real Estate Development has 3 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Vyne Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Vyne Residences be completed?
The completion date registered with the Dubai Land Department is November 2026. At the pace of its recent inspections the site would reach 100% around August 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Vyne Residences is built?
80%, measured at the Land Department site inspection on 22 April 2026. The Land Department engineers have inspected the site 5 times since June 2024.
Is The Vyne Residences delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of November 2026.
Who is building The Vyne Residences?
The registered developer is Metrical Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for The Vyne Residences?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.