The One At Jumeirah Village Triangle construction progress
The register lists The One At Jumeirah Village Triangle in Jumeirah Village Triangle as complete, with a registered completion date of January 2022. Its last site inspection on record was in September 2024. The developer is T F G Real Estate.
100%
Built, at the site inspection of 19 September 2024
Construction complete
- Registered completion date
- January 2022
- Construction started
- February 2016
- First registered
- November 2016
- Developer
- T F G Real Estate
- Community
- Jumeirah Village Triangle
- Units
- 593
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- ذا ون ات جميرا فيلج تراينجل
- Project number
- 1802
- Site inspections
- 17
Schedule
The register lists The One At Jumeirah Village Triangle as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
19 September 2024
100%+1.9 pts
30 December 2021
98%+0.0 pts
17 November 2021
98%+3.0 pts
30 June 2021
95%+4.0 pts
28 February 2021
91%+9.7 pts
26 October 2020
81%+8.4 pts
2 July 2020
73%+2.8 pts
21 April 2020
70%+8.5 pts
18 December 2019
62%+11 pts
28 August 2019
51%+13 pts
Context
Jumeirah Village Triangle has 29 projects under construction, 27% built on average.
Own a unit in The One At Jumeirah Village Triangle?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the The One At Jumeirah Village Triangle handover date?
- Construction of The One At Jumeirah Village Triangle is recorded as complete, with a registered completion date of January 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on The One At Jumeirah Village Triangle?
- The One At Jumeirah Village Triangle was 100% built at the site inspection on 19 September 2024. The site has been inspected 17 times since March 2017. The Land Department took 161 site photos at its inspections.
- Is The One At Jumeirah Village Triangle delayed?
- The register lists construction as complete.
- Who is building The One At Jumeirah Village Triangle?
- The registered developer is T F G Real Estate.
- Which bank holds the escrow account for The One At Jumeirah Village Triangle?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Paradise OneNearby in Jumeirah Village Triangle. 70%, Due April 2027.
- Silver StallionsNearby in Jumeirah Village Triangle. 12%, Due December 2017, passed.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Volga TowerNearby in Jumeirah Village Triangle. 51%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)