161 photos from 17 site inspections, newest first. The percentage is how much of The One At Jumeirah Village Triangle was built on the day of each visit.

19 September 2024100% built

30 December 202198% built

17 November 202198% built

30 June 202195% built

28 February 202191% built

26 October 202081% built

2 July 202073% built

21 April 202070% built

18 December 201962% built

28 August 201951% built

7 April 201938% built

14 November 201830% built

16 August 201826% built

3 April 201821% built

23 November 201713% built

15 August 20177.8% built

20 March 20175.2% built

Back to The One At Jumeirah Village Triangle construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.