Taraf 2 Residence construction progress

The register lists Taraf 2 Residence in Jumeirah Village Triangle as complete, with a registered completion date of January 2023. Its last site inspection on record was in January 2023. The developer is Taraf Properties Fzco.

100%

Built, at the site inspection of 19 January 2023

Construction complete

Registered completion date
January 2023
Construction started
January 2021
First registered
November 2021
Developer
Taraf Properties Fzco
Units
94
Escrow bank
First Abu Dhabi Bank
Name in Arabic
Taraf 2 Residence
Project number
2312
Site inspections
5

Schedule

The register lists Taraf 2 Residence as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 January 2023

100%+16 pts

  • Taraf 2 Residence construction site, inspection photo 1, 19 January 2023
  • Taraf 2 Residence construction site, inspection photo 2, 19 January 2023
  • Taraf 2 Residence construction site, inspection photo 3, 19 January 2023
  • Taraf 2 Residence construction site, inspection photo 4, 19 January 2023

9 August 2022

84%+3.5 pts

  • Taraf 2 Residence construction site, inspection photo 1, 9 August 2022
  • Taraf 2 Residence construction site, inspection photo 2, 9 August 2022
  • Taraf 2 Residence construction site, inspection photo 3, 9 August 2022
  • Taraf 2 Residence construction site, inspection photo 4, 9 August 2022

30 June 2022

80%+8.1 pts

  • Taraf 2 Residence construction site, inspection photo 1, 30 June 2022
  • Taraf 2 Residence construction site, inspection photo 2, 30 June 2022
  • Taraf 2 Residence construction site, inspection photo 3, 30 June 2022
  • Taraf 2 Residence construction site, inspection photo 4, 30 June 2022

25 May 2022

72%+28 pts

  • Taraf 2 Residence construction site, inspection photo 1, 25 May 2022
  • Taraf 2 Residence construction site, inspection photo 2, 25 May 2022
  • Taraf 2 Residence construction site, inspection photo 3, 25 May 2022
  • Taraf 2 Residence construction site, inspection photo 4, 25 May 2022

30 October 2021

44%

  • Taraf 2 Residence construction site, inspection photo 1, 30 October 2021
  • Taraf 2 Residence construction site, inspection photo 2, 30 October 2021
  • Taraf 2 Residence construction site, inspection photo 3, 30 October 2021
  • Taraf 2 Residence construction site, inspection photo 4, 30 October 2021

All 57 site photos, by inspection date

Context

Jumeirah Village Triangle has 29 projects under construction, 27% built on average.

Taraf Properties Fzco has 1 project under construction in Dubai, none past their registered completion dates.

Own a unit in Taraf 2 Residence?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Taraf 2 Residence handover date?
Construction of Taraf 2 Residence is recorded as complete, with a registered completion date of January 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Taraf 2 Residence?
Taraf 2 Residence was 100% built at the site inspection on 19 January 2023. The site has been inspected 5 times since October 2021. The Land Department took 57 site photos at its inspections.
Is Taraf 2 Residence delayed?
The register lists construction as complete.
Who is building Taraf 2 Residence?
The registered developer is Taraf Properties Fzco. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Taraf 2 Residence?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.