Taraf 3 Residence construction progress

The registered completion date for Taraf 3 Residence is March 2028. At the last site inspection, in October 2026, it was 6.9% built. The developer is Taraf Properties Fzco.

6.9%

Built, at the site inspection of 23 October 2026

Running behind its date

Registered completion date
March 2028
Finish at recent pace
August 2039
Construction started
November 2025
First registered
November 2025
Developer
Taraf Properties Fzco
Units
151
Escrow bank
First Abu Dhabi Bank
Name in Arabic
تاراف 3 ريذدنس
Project number
4192
Site inspections
3

Schedule

Between November 2025 and October 2026 the site added about 0.6 points a month. At that rate it would finish around August 2039, more than three months after its registered date of March 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 October 2026

6.9%+1.1 pts

  • Taraf 3 Residence construction site, inspection photo 1, 23 October 2026
  • Taraf 3 Residence construction site, inspection photo 2, 23 October 2026
  • Taraf 3 Residence construction site, inspection photo 3, 23 October 2026
  • Taraf 3 Residence construction site, inspection photo 4, 23 October 2026

5 May 2026

5.9%+5.9 pts

  • Taraf 3 Residence construction site, inspection photo 1, 5 May 2026
  • Taraf 3 Residence construction site, inspection photo 2, 5 May 2026
  • Taraf 3 Residence construction site, inspection photo 3, 5 May 2026

9 November 2025

0%

  • Taraf 3 Residence construction site, inspection photo 1, 9 November 2025
  • Taraf 3 Residence construction site, inspection photo 2, 9 November 2025

All 10 site photos, by inspection date

Context

Own a unit in Taraf 3 Residence?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Taraf 3 Residence handover date?
The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2039. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Taraf 3 Residence?
Taraf 3 Residence was 6.9% built at the site inspection on 23 October 2026. The site has been inspected 3 times since November 2025. The Land Department took 10 site photos at its inspections.
Is Taraf 3 Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Taraf 3 Residence?
The registered developer is Taraf Properties Fzco.
Which bank holds the escrow account for Taraf 3 Residence?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.