Taraf 3 Residence construction progress

Taraf 3 Residence is 5.9% built at the Land Department inspection of May 2026. Developer Taraf Properties Fzco. Completion registered for March 2028.

5.9%

Built, at the Land Department site inspection of 5 May 2026

Running behind its date

Completion date (Land Department)
March 2028
Finish at recent pace
February 2034
Construction started
November 2025
Registered with the Land Department
November 2025
Developer
Taraf Properties Fzco
Units
151
Escrow bank
First Abu Dhabi Bank
Name in Arabic
تاراف 3 ريذدنس
Land Department project number
4192
Land Department site inspections
2

Schedule

Between November 2025 and May 2026 the site added about 1.0 points a month. At that rate it would finish around February 2034, more than three months after the March 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

5 May 2026

5.9%+5.9 pts

  • Taraf 3 Residence construction site, Land Department inspection photo 1, 5 May 2026
  • Taraf 3 Residence construction site, Land Department inspection photo 2, 5 May 2026
  • Taraf 3 Residence construction site, Land Department inspection photo 3, 5 May 2026

9 November 2025

0%

  • Taraf 3 Residence construction site, Land Department inspection photo 1, 9 November 2025
  • Taraf 3 Residence construction site, Land Department inspection photo 2, 9 November 2025

All 5 site photos, by inspection date

Context

Own a unit in Taraf 3 Residence?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Taraf 3 Residence be completed?
The completion date registered with the Dubai Land Department is March 2028. At the pace of its recent inspections the site would reach 100% around February 2034. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Taraf 3 Residence is built?
5.9%, measured at the Land Department site inspection on 5 May 2026. The Land Department engineers have inspected the site 2 times since November 2025.
Is Taraf 3 Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Taraf 3 Residence?
The registered developer is Taraf Properties Fzco.
Which bank holds the escrow account for Taraf 3 Residence?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.