Taraf 3 Residence construction progress
The registered completion date for Taraf 3 Residence is March 2028. At the last site inspection, in October 2026, it was 6.9% built. The developer is Taraf Properties Fzco.
6.9%
Built, at the site inspection of 23 October 2026
Running behind its date
- Registered completion date
- March 2028
- Finish at recent pace
- August 2039
- Construction started
- November 2025
- First registered
- November 2025
- Developer
- Taraf Properties Fzco
- Units
- 151
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- تاراف 3 ريذدنس
- Project number
- 4192
- Site inspections
- 3
Schedule
Between November 2025 and October 2026 the site added about 0.6 points a month. At that rate it would finish around August 2039, more than three months after its registered date of March 2028.
Site inspections
23 October 2026
6.9%+1.1 pts
5 May 2026
5.9%+5.9 pts
9 November 2025
0%
Context
Own a unit in Taraf 3 Residence?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Taraf 3 Residence handover date?
- The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2039. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Taraf 3 Residence?
- Taraf 3 Residence was 6.9% built at the site inspection on 23 October 2026. The site has been inspected 3 times since November 2025. The Land Department took 10 site photos at its inspections.
- Is Taraf 3 Residence delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
- Who is building Taraf 3 Residence?
- The registered developer is Taraf Properties Fzco.
- Which bank holds the escrow account for Taraf 3 Residence?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.