Sonate Residences By Condor construction progress

Sonate Residences By Condor in Jumeirah Village Triangle is 66% built at the Land Department inspection of September 2026. Developer Condor Concept 7 View Real Estate Development.

66%

Built, at the Land Department site inspection of 4 September 2026

Finish at recent pace
May 2027
Construction started
March 2024
Registered with the Land Department
February 2024
Developer
Condor Concept 7 View Real Estate Development
Units
215
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
سونيت ريزيدنسيز باي كوندور
Land Department project number
2923
Land Department site inspections
7

Schedule

Since December 2025 Sonate Residences By Condor has added about 4.2 points a month. At that rate the site reaches 100% around May 2027. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%20252026
Progress at each Land Department site inspection

Site inspections

4 September 2026

66%+8.1 pts

  • Sonate Residences By Condor construction site, Land Department inspection photo 1, 4 September 2026
  • Sonate Residences By Condor construction site, Land Department inspection photo 2, 4 September 2026
  • Sonate Residences By Condor construction site, Land Department inspection photo 3, 4 September 2026
  • Sonate Residences By Condor construction site, Land Department inspection photo 4, 4 September 2026

10 July 2026

58%+17 pts

  • Sonate Residences By Condor construction site, Land Department inspection photo 1, 10 July 2026
  • Sonate Residences By Condor construction site, Land Department inspection photo 2, 10 July 2026
  • Sonate Residences By Condor construction site, Land Department inspection photo 3, 10 July 2026
  • Sonate Residences By Condor construction site, Land Department inspection photo 4, 10 July 2026

27 April 2026

41%+11 pts

  • Sonate Residences By Condor construction site, Land Department inspection photo 1, 27 April 2026
  • Sonate Residences By Condor construction site, Land Department inspection photo 2, 27 April 2026
  • Sonate Residences By Condor construction site, Land Department inspection photo 3, 27 April 2026
  • Sonate Residences By Condor construction site, Land Department inspection photo 4, 27 April 2026

19 December 2025

31%+14 pts

  • Sonate Residences By Condor construction site, Land Department inspection photo 1, 19 December 2025
  • Sonate Residences By Condor construction site, Land Department inspection photo 2, 19 December 2025
  • Sonate Residences By Condor construction site, Land Department inspection photo 3, 19 December 2025
  • Sonate Residences By Condor construction site, Land Department inspection photo 4, 19 December 2025

19 June 2025

17%+4.0 pts

  • Sonate Residences By Condor construction site, Land Department inspection photo 1, 19 June 2025
  • Sonate Residences By Condor construction site, Land Department inspection photo 2, 19 June 2025
  • Sonate Residences By Condor construction site, Land Department inspection photo 3, 19 June 2025
  • Sonate Residences By Condor construction site, Land Department inspection photo 4, 19 June 2025

14 January 2025

13%+13 pts

  • Sonate Residences By Condor construction site, Land Department inspection photo 1, 14 January 2025
  • Sonate Residences By Condor construction site, Land Department inspection photo 2, 14 January 2025
  • Sonate Residences By Condor construction site, Land Department inspection photo 3, 14 January 2025

24 January 2024

0%

  • Sonate Residences By Condor construction site, Land Department inspection photo 1, 24 January 2024
  • Sonate Residences By Condor construction site, Land Department inspection photo 2, 24 January 2024

All 68 site photos, by inspection date

Context

Jumeirah Village Triangle has 31 projects under construction, 28% built on average.

Own a unit in Sonate Residences By Condor?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Sonate Residences By Condor be completed?
The Land Department has no completion date on record for Sonate Residences By Condor yet.
How much of Sonate Residences By Condor is built?
66%, measured at the Land Department site inspection on 4 September 2026. The Land Department engineers have inspected the site 7 times since January 2024.
Who is building Sonate Residences By Condor?
The registered developer is Condor Concept 7 View Real Estate Development.
Which bank holds the escrow account for Sonate Residences By Condor?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.