Sonate Residences By Condor construction progress

No completion date is registered for Sonate Residences By Condor in Jumeirah Village Triangle yet. At the last site inspection, in October 2026, it was 74% built. The developer is Condor Sonate Real Estate Development.

74%

Built, at the site inspection of 20 October 2026

Finish at recent pace
April 2027
Construction started
March 2024
First registered
February 2024
Developer
Condor Sonate Real Estate Development
Units
215
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
سونيت ريزيدنسيز باي كوندور
Project number
2923
Site inspections
8

Schedule

Since December 2025 Sonate Residences By Condor has added about 4.4 points a month. At that rate the site reaches 100% around April 2027. No completion date is on record to compare it with.

0%25%50%75%100%20252026
Progress at each site inspection

Site inspections

20 October 2026

74%+8.4 pts

  • Sonate Residences By Condor construction site, inspection photo 1, 20 October 2026
  • Sonate Residences By Condor construction site, inspection photo 2, 20 October 2026
  • Sonate Residences By Condor construction site, inspection photo 3, 20 October 2026
  • Sonate Residences By Condor construction site, inspection photo 4, 20 October 2026

4 September 2026

66%+8.1 pts

  • Sonate Residences By Condor construction site, inspection photo 1, 4 September 2026
  • Sonate Residences By Condor construction site, inspection photo 2, 4 September 2026
  • Sonate Residences By Condor construction site, inspection photo 3, 4 September 2026
  • Sonate Residences By Condor construction site, inspection photo 4, 4 September 2026

10 July 2026

58%+17 pts

  • Sonate Residences By Condor construction site, inspection photo 1, 10 July 2026
  • Sonate Residences By Condor construction site, inspection photo 2, 10 July 2026
  • Sonate Residences By Condor construction site, inspection photo 3, 10 July 2026
  • Sonate Residences By Condor construction site, inspection photo 4, 10 July 2026

27 April 2026

41%+11 pts

  • Sonate Residences By Condor construction site, inspection photo 1, 27 April 2026
  • Sonate Residences By Condor construction site, inspection photo 2, 27 April 2026
  • Sonate Residences By Condor construction site, inspection photo 3, 27 April 2026
  • Sonate Residences By Condor construction site, inspection photo 4, 27 April 2026

19 December 2025

31%+14 pts

  • Sonate Residences By Condor construction site, inspection photo 1, 19 December 2025
  • Sonate Residences By Condor construction site, inspection photo 2, 19 December 2025
  • Sonate Residences By Condor construction site, inspection photo 3, 19 December 2025
  • Sonate Residences By Condor construction site, inspection photo 4, 19 December 2025

19 June 2025

17%+4.0 pts

  • Sonate Residences By Condor construction site, inspection photo 1, 19 June 2025
  • Sonate Residences By Condor construction site, inspection photo 2, 19 June 2025
  • Sonate Residences By Condor construction site, inspection photo 3, 19 June 2025
  • Sonate Residences By Condor construction site, inspection photo 4, 19 June 2025

14 January 2025

13%+13 pts

  • Sonate Residences By Condor construction site, inspection photo 1, 14 January 2025
  • Sonate Residences By Condor construction site, inspection photo 2, 14 January 2025
  • Sonate Residences By Condor construction site, inspection photo 3, 14 January 2025

24 January 2024

0%

  • Sonate Residences By Condor construction site, inspection photo 1, 24 January 2024
  • Sonate Residences By Condor construction site, inspection photo 2, 24 January 2024

All 78 site photos, by inspection date

Context

Jumeirah Village Triangle has 29 projects under construction, 27% built on average.

Own a unit in Sonate Residences By Condor?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sonate Residences By Condor handover date?
No completion date is on record for Sonate Residences By Condor yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Sonate Residences By Condor?
Sonate Residences By Condor was 74% built at the site inspection on 20 October 2026. The site has been inspected 8 times since January 2024. The Land Department took 78 site photos at its inspections.
Who is building Sonate Residences By Condor?
The registered developer is Condor Sonate Real Estate Development.
Which bank holds the escrow account for Sonate Residences By Condor?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.