Park One construction progress

The register lists Park One in Jumeirah Village Triangle as complete, with a registered completion date of April 2018. Its last site inspection on record was in July 2018. The developer is Swiss Property Development.

100%

Built, at the site inspection of 2 July 2018

Construction complete

Registered completion date
April 2018
Construction started
October 2015
First registered
November 2015
Developer
Swiss Property Development
Units
57
Escrow bank
Noor Bank
Name in Arabic
بارك ون
Project number
1694
Site inspections
6

Schedule

The register lists Park One as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201620172018
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 July 2018

100%+22 pts

  • Park One construction site, inspection photo 1, 2 July 2018
  • Park One construction site, inspection photo 2, 2 July 2018
  • Park One construction site, inspection photo 3, 2 July 2018
  • Park One construction site, inspection photo 4, 2 July 2018

17 December 2017

78%+25 pts

  • Park One construction site, inspection photo 1, 17 December 2017
  • Park One construction site, inspection photo 2, 17 December 2017
  • Park One construction site, inspection photo 3, 17 December 2017
  • Park One construction site, inspection photo 4, 17 December 2017

29 August 2017

53%+33 pts

  • Park One construction site, inspection photo 1, 29 August 2017
  • Park One construction site, inspection photo 2, 29 August 2017
  • Park One construction site, inspection photo 3, 29 August 2017
  • Park One construction site, inspection photo 4, 29 August 2017

28 February 2017

20%+14 pts

  • Park One construction site, inspection photo 1, 28 February 2017
  • Park One construction site, inspection photo 2, 28 February 2017
  • Park One construction site, inspection photo 3, 28 February 2017
  • Park One construction site, inspection photo 4, 28 February 2017

26 October 2016

6.7%+3.7 pts

  • Park One construction site, inspection photo 1, 26 October 2016
  • Park One construction site, inspection photo 2, 26 October 2016
  • Park One construction site, inspection photo 3, 26 October 2016
  • Park One construction site, inspection photo 4, 26 October 2016

29 February 2016

3.0%

  • Park One construction site, inspection photo 1, 29 February 2016
  • Park One construction site, inspection photo 2, 29 February 2016

All 37 site photos, by inspection date

Context

Jumeirah Village Triangle has 29 projects under construction, 27% built on average.

Own a unit in Park One?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Park One handover date?
Construction of Park One is recorded as complete, with a registered completion date of April 2018. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Park One?
Park One was 100% built at the site inspection on 2 July 2018. The site has been inspected 6 times since February 2016. The Land Department took 37 site photos at its inspections.
Is Park One delayed?
The register lists construction as complete.
Who is building Park One?
The registered developer is Swiss Property Development.
Which bank holds the escrow account for Park One?
Noor Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.