Park One construction photos
37 photos from 6 site inspections, newest first. The percentage is how much of Park One was built on the day of each visit.
2 July 2018100% built
17 December 201778% built
29 August 201753% built
28 February 201720% built
26 October 20166.7% built
29 February 20163.0% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.