Zenith Tower J1 construction progress

Zenith Tower J1 in Jumeirah Village Circle is 72% built at the Land Department inspection of August 2026. Developer Zenith Ventures Real Estate Development. Completion registered for December 2026.

72%

Built, at the Land Department site inspection of 4 August 2026

On pace for its date

Completion date (Land Department)
December 2026
Finish at recent pace
January 2027
Construction started
September 2023
Registered with the Land Department
September 2025
Developer
Zenith Ventures Real Estate Development
Units
76
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
برج زينيث J1
Land Department project number
3628
Land Department site inspections
3

Schedule

Since April 2026 Zenith Tower J1 has added about 5.1 points a month. That puts 100% around January 2027, within three months of its registered completion date of December 2026.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

4 August 2026

72%+17 pts

  • Zenith Tower J1 construction site, Land Department inspection photo 1, 4 August 2026
  • Zenith Tower J1 construction site, Land Department inspection photo 2, 4 August 2026
  • Zenith Tower J1 construction site, Land Department inspection photo 3, 4 August 2026
  • Zenith Tower J1 construction site, Land Department inspection photo 4, 4 August 2026

25 April 2026

55%+19 pts

  • Zenith Tower J1 construction site, Land Department inspection photo 1, 25 April 2026
  • Zenith Tower J1 construction site, Land Department inspection photo 2, 25 April 2026
  • Zenith Tower J1 construction site, Land Department inspection photo 3, 25 April 2026
  • Zenith Tower J1 construction site, Land Department inspection photo 4, 25 April 2026

8 May 2025

37%

  • Zenith Tower J1 construction site, Land Department inspection photo 1, 8 May 2025
  • Zenith Tower J1 construction site, Land Department inspection photo 2, 8 May 2025
  • Zenith Tower J1 construction site, Land Department inspection photo 3, 8 May 2025
  • Zenith Tower J1 construction site, Land Department inspection photo 4, 8 May 2025

All 28 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Own a unit in Zenith Tower J1?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Zenith Tower J1 be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around January 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Zenith Tower J1 is built?
72%, measured at the Land Department site inspection on 4 August 2026. The Land Department engineers have inspected the site 3 times since May 2025.
Is Zenith Tower J1 delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of December 2026.
Who is building Zenith Tower J1?
The registered developer is Zenith Ventures Real Estate Development.
Which bank holds the escrow account for Zenith Tower J1?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.