Xenia Residence construction progress

Xenia Residence in Jumeirah Village Circle is 42% built at the Land Department inspection of April 2026. Developer N Y X Real Estate Development. Completion registered for March 2027.

42%

Built, at the Land Department site inspection of 23 April 2026

Running behind its date

Completion date (Land Department)
March 2027
Finish at recent pace
February 2029
Construction started
September 2025
Registered with the Land Department
October 2025
Developer
N Y X Real Estate Development
Units
73
Escrow bank
United Arab Bank
Name in Arabic
زينيا ريزيدنس
Land Department project number
3880
Land Department site inspections
2

Schedule

Between September 2025 and April 2026 the site added about 1.7 points a month. At that rate it would finish around February 2029, more than three months after the March 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 April 2026

42%+13 pts

  • Xenia Residence construction site, Land Department inspection photo 1, 23 April 2026
  • Xenia Residence construction site, Land Department inspection photo 2, 23 April 2026
  • Xenia Residence construction site, Land Department inspection photo 3, 23 April 2026
  • Xenia Residence construction site, Land Department inspection photo 4, 23 April 2026

8 September 2025

29%

  • Xenia Residence construction site, Land Department inspection photo 1, 8 September 2025
  • Xenia Residence construction site, Land Department inspection photo 2, 8 September 2025
  • Xenia Residence construction site, Land Department inspection photo 3, 8 September 2025
  • Xenia Residence construction site, Land Department inspection photo 4, 8 September 2025

All 17 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Own a unit in Xenia Residence?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Xenia Residence be completed?
The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around February 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Xenia Residence is built?
42%, measured at the Land Department site inspection on 23 April 2026. The Land Department engineers have inspected the site 2 times since September 2025.
Is Xenia Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Xenia Residence?
The registered developer is N Y X Real Estate Development.
Which bank holds the escrow account for Xenia Residence?
United Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.