Xenia Residence construction progress
The registered completion date for Xenia Residence in Jumeirah Village Circle is March 2027. At the last site inspection, in October 2026, it was 52% built. The developer is N Y X Real Estate Development.
52%
Built, at the site inspection of 15 October 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- March 2029
- Construction started
- September 2025
- First registered
- October 2025
- Developer
- N Y X Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 73
- Escrow bank
- United Arab Bank
- Name in Arabic
- زينيا ريزيدنس
- Project number
- 3880
- Site inspections
- 3
Schedule
Between April 2026 and October 2026 the site added about 1.7 points a month. At that rate it would finish around March 2029, more than three months after its registered date of March 2027.
Site inspections
15 October 2026
52%+9.5 pts
23 April 2026
42%+13 pts
8 September 2025
29%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Xenia Residence?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Xenia Residence handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Xenia Residence?
- Xenia Residence was 52% built at the site inspection on 15 October 2026. The site has been inspected 3 times since September 2025. The Land Department took 30 site photos at its inspections.
- Is Xenia Residence delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Xenia Residence?
- The registered developer is N Y X Real Estate Development.
- Which bank holds the escrow account for Xenia Residence?
- United Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)