Xenia Residence construction progress

The registered completion date for Xenia Residence in Jumeirah Village Circle is March 2027. At the last site inspection, in October 2026, it was 52% built. The developer is N Y X Real Estate Development.

52%

Built, at the site inspection of 15 October 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
March 2029
Construction started
September 2025
First registered
October 2025
Developer
N Y X Real Estate Development
Units
73
Escrow bank
United Arab Bank
Name in Arabic
زينيا ريزيدنس
Project number
3880
Site inspections
3

Schedule

Between April 2026 and October 2026 the site added about 1.7 points a month. At that rate it would finish around March 2029, more than three months after its registered date of March 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 October 2026

52%+9.5 pts

  • Xenia Residence construction site, inspection photo 1, 15 October 2026
  • Xenia Residence construction site, inspection photo 2, 15 October 2026
  • Xenia Residence construction site, inspection photo 3, 15 October 2026
  • Xenia Residence construction site, inspection photo 4, 15 October 2026

23 April 2026

42%+13 pts

  • Xenia Residence construction site, inspection photo 1, 23 April 2026
  • Xenia Residence construction site, inspection photo 2, 23 April 2026
  • Xenia Residence construction site, inspection photo 3, 23 April 2026
  • Xenia Residence construction site, inspection photo 4, 23 April 2026

8 September 2025

29%

  • Xenia Residence construction site, inspection photo 1, 8 September 2025
  • Xenia Residence construction site, inspection photo 2, 8 September 2025
  • Xenia Residence construction site, inspection photo 3, 8 September 2025
  • Xenia Residence construction site, inspection photo 4, 8 September 2025

All 30 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Xenia Residence?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Xenia Residence handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Xenia Residence?
Xenia Residence was 52% built at the site inspection on 15 October 2026. The site has been inspected 3 times since September 2025. The Land Department took 30 site photos at its inspections.
Is Xenia Residence delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Xenia Residence?
The registered developer is N Y X Real Estate Development.
Which bank holds the escrow account for Xenia Residence?
United Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.