Vue By Crystal Bay construction progress
Vue By Crystal Bay in Jumeirah Village Circle was registered to complete in October 2026 and is still under construction. At the last site inspection, in August 2026, it was 68% built. The developer is Crystal Bay Development.
68%
Built, at the site inspection of 27 August 2026
2 months past its registered completion date
- Registered completion date
- October 2026
- Finish at recent pace
- April 2027
- Construction started
- April 2024
- First registered
- June 2024
- Developer
- Crystal Bay Development
- Community
- Jumeirah Village Circle
- Units
- 176
- Escrow bank
- Mashreq Bank
- Name in Arabic
- فيو باي كريستال باي
- Project number
- 3090
- Site inspections
- 6
Schedule
Vue By Crystal Bay was registered to complete in October 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 4.1 points a month. Kept at that rate, the site would reach 100% around April 2027.
Site inspections
27 August 2026
68%+14 pts
9 June 2026
54%+19 pts
28 January 2026
36%+14 pts
15 September 2025
21%+6.7 pts
12 May 2025
15%+15 pts
15 May 2024
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Vue By Crystal Bay?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Vue By Crystal Bay handover date?
- The registered completion date was October 2026, and the register still lists Vue By Crystal Bay as under construction. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Vue By Crystal Bay?
- Vue By Crystal Bay was 68% built at the site inspection on 27 August 2026. The site has been inspected 6 times since May 2024. The Land Department took 50 site photos at its inspections.
- Is Vue By Crystal Bay delayed?
- Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
- Who is building Vue By Crystal Bay?
- The registered developer is Crystal Bay Development.
- Which bank holds the escrow account for Vue By Crystal Bay?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)