Vue By Crystal Bay construction progress

Vue By Crystal Bay in Jumeirah Village Circle is 68% built at the Land Department inspection of August 2026. Developer Crystal Bay Development. Completion registered for October 2026.

68%

Built, at the Land Department site inspection of 27 August 2026

0 months past its registered completion date

Completion date (Land Department)
October 2026
Finish at recent pace
April 2027
Construction started
April 2024
Registered with the Land Department
June 2024
Developer
Crystal Bay Development
Units
176
Escrow bank
Mashreq Bank
Name in Arabic
فيو باي كريستال باي
Land Department project number
3090
Land Department site inspections
6

Schedule

Vue By Crystal Bay was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 4.1 points a month. Kept at that rate, the site would reach 100% around April 2027.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

27 August 2026

68%+14 pts

  • Vue By Crystal Bay construction site, Land Department inspection photo 1, 27 August 2026
  • Vue By Crystal Bay construction site, Land Department inspection photo 2, 27 August 2026
  • Vue By Crystal Bay construction site, Land Department inspection photo 3, 27 August 2026
  • Vue By Crystal Bay construction site, Land Department inspection photo 4, 27 August 2026

9 June 2026

54%+19 pts

  • Vue By Crystal Bay construction site, Land Department inspection photo 1, 9 June 2026
  • Vue By Crystal Bay construction site, Land Department inspection photo 2, 9 June 2026
  • Vue By Crystal Bay construction site, Land Department inspection photo 3, 9 June 2026
  • Vue By Crystal Bay construction site, Land Department inspection photo 4, 9 June 2026

28 January 2026

36%+14 pts

  • Vue By Crystal Bay construction site, Land Department inspection photo 1, 28 January 2026
  • Vue By Crystal Bay construction site, Land Department inspection photo 2, 28 January 2026
  • Vue By Crystal Bay construction site, Land Department inspection photo 3, 28 January 2026
  • Vue By Crystal Bay construction site, Land Department inspection photo 4, 28 January 2026

15 September 2025

21%+6.7 pts

  • Vue By Crystal Bay construction site, Land Department inspection photo 1, 15 September 2025
  • Vue By Crystal Bay construction site, Land Department inspection photo 2, 15 September 2025
  • Vue By Crystal Bay construction site, Land Department inspection photo 3, 15 September 2025
  • Vue By Crystal Bay construction site, Land Department inspection photo 4, 15 September 2025

12 May 2025

15%+15 pts

  • Vue By Crystal Bay construction site, Land Department inspection photo 1, 12 May 2025
  • Vue By Crystal Bay construction site, Land Department inspection photo 2, 12 May 2025
  • Vue By Crystal Bay construction site, Land Department inspection photo 3, 12 May 2025
  • Vue By Crystal Bay construction site, Land Department inspection photo 4, 12 May 2025

15 May 2024

0%

  • Vue By Crystal Bay construction site, Land Department inspection photo 1, 15 May 2024
  • Vue By Crystal Bay construction site, Land Department inspection photo 2, 15 May 2024

All 50 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Own a unit in Vue By Crystal Bay?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Vue By Crystal Bay be completed?
The completion date registered with the Dubai Land Department is October 2026. At the pace of its recent inspections the site would reach 100% around April 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Vue By Crystal Bay is built?
68%, measured at the Land Department site inspection on 27 August 2026. The Land Department engineers have inspected the site 6 times since May 2024.
Is Vue By Crystal Bay delayed?
Yes. Its registered completion date of October 2026 has passed and the Land Department still lists it as under construction.
Who is building Vue By Crystal Bay?
The registered developer is Crystal Bay Development.
Which bank holds the escrow account for Vue By Crystal Bay?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.