The Borough construction progress

The registered completion date for The Borough in Jumeirah Village Circle is March 2028. At the last site inspection, in August 2026, it was 5.5% built. The developer is Iconic Vista Real Estate Development.

5.5%

Built, at the site inspection of 11 August 2026

Running behind its date

Registered completion date
March 2028
Finish at recent pace
February 2051
Construction started
August 2025
First registered
September 2025
Developer
Iconic Vista Real Estate Development
Units
157
Escrow bank
Emirates NBD
Name in Arabic
The Borough
Project number
3833
Site inspections
3

Schedule

Between April 2026 and August 2026 the site added about 0.3 points a month. At that rate it would finish around February 2051, more than three months after its registered date of March 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 August 2026

5.5%+1.2 pts

  • The Borough construction site, inspection photo 1, 11 August 2026
  • The Borough construction site, inspection photo 2, 11 August 2026

23 April 2026

4.3%+4.3 pts

  • The Borough construction site, inspection photo 1, 23 April 2026
  • The Borough construction site, inspection photo 2, 23 April 2026
  • The Borough construction site, inspection photo 3, 23 April 2026
  • The Borough construction site, inspection photo 4, 23 April 2026

28 July 2025

0%

  • The Borough construction site, inspection photo 1, 28 July 2025
  • The Borough construction site, inspection photo 2, 28 July 2025

All 9 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in The Borough?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Borough handover date?
The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2051. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Borough?
The Borough was 5.5% built at the site inspection on 11 August 2026. The site has been inspected 3 times since July 2025. The Land Department took 9 site photos at its inspections.
Is The Borough delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building The Borough?
The registered developer is Iconic Vista Real Estate Development.
Which bank holds the escrow account for The Borough?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.