The Borough construction progress

The Borough in Jumeirah Village Circle is 5.5% built at the Land Department inspection of August 2026. Developer Iconic Vista Real Estate Development. Completion registered for March 2028.

5.5%

Built, at the Land Department site inspection of 11 August 2026

Running behind its date

Completion date (Land Department)
March 2028
Finish at recent pace
February 2051
Construction started
August 2025
Registered with the Land Department
September 2025
Developer
Iconic Vista Real Estate Development
Units
157
Escrow bank
Emirates NBD
Name in Arabic
The Borough
Land Department project number
3833
Land Department site inspections
3

Schedule

Between April 2026 and August 2026 the site added about 0.3 points a month. At that rate it would finish around February 2051, more than three months after the March 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

11 August 2026

5.5%+1.2 pts

  • The Borough construction site, Land Department inspection photo 1, 11 August 2026
  • The Borough construction site, Land Department inspection photo 2, 11 August 2026

23 April 2026

4.3%+4.3 pts

  • The Borough construction site, Land Department inspection photo 1, 23 April 2026
  • The Borough construction site, Land Department inspection photo 2, 23 April 2026
  • The Borough construction site, Land Department inspection photo 3, 23 April 2026
  • The Borough construction site, Land Department inspection photo 4, 23 April 2026

28 July 2025

0%

  • The Borough construction site, Land Department inspection photo 1, 28 July 2025
  • The Borough construction site, Land Department inspection photo 2, 28 July 2025

All 9 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Own a unit in The Borough?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Borough be completed?
The completion date registered with the Dubai Land Department is March 2028. At the pace of its recent inspections the site would reach 100% around February 2051. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Borough is built?
5.5%, measured at the Land Department site inspection on 11 August 2026. The Land Department engineers have inspected the site 3 times since July 2025.
Is The Borough delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building The Borough?
The registered developer is Iconic Vista Real Estate Development.
Which bank holds the escrow account for The Borough?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.