Sunset Grove Homes construction progress
Sunset Grove Homes in Jumeirah Village Circle was registered to complete in September 2025 and is still under construction. At the last site inspection, in April 2026, it was 28% built. The developer is S N K Real Estate Development.
28%
Built, at the site inspection of 28 April 2026
14 months past its registered completion date
- Registered completion date
- September 2025
- Finish at recent pace
- June 2028
- Construction started
- March 2024
- First registered
- July 2024
- Developer
- S N K Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 8
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- صن ست غروف هومز
- Project number
- 3014
- Site inspections
- 4
Schedule
Sunset Grove Homes was registered to complete in September 2025, 14 months ago, and is still under construction. Over the last year of inspections it has added about 2.8 points a month. Kept at that rate, the site would reach 100% around June 2028.
Site inspections
28 April 2026
28%+13 pts
12 December 2025
14%+12 pts
23 July 2025
2.3%+2.3 pts
10 May 2024
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in Sunset Grove Homes?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Sunset Grove Homes handover date?
- The registered completion date was September 2025, and the register still lists Sunset Grove Homes as under construction. At the pace of its recent inspections the site would reach 100% around June 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Sunset Grove Homes?
- Sunset Grove Homes was 28% built at the site inspection on 28 April 2026. The site has been inspected 4 times since May 2024. The Land Department took 18 site photos at its inspections.
- Is Sunset Grove Homes delayed?
- Yes. Its registered completion date of September 2025 has passed and the project is still listed as under construction.
- Who is building Sunset Grove Homes?
- The registered developer is S N K Real Estate Development.
- Which bank holds the escrow account for Sunset Grove Homes?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.











.jpg&w=3840&q=75)