Stonehenge Residences construction progress

The register lists Stonehenge Residences in Jumeirah Village Circle as complete, with a registered completion date of March 2025. Its last site inspection on record was in January 2026. The developer is Segrex Development.

100%

Built, at the site inspection of 22 January 2026

Construction complete

Registered completion date
March 2025
Construction started
February 2023
First registered
May 2023
Developer
Segrex Development
Units
156
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
ستونج ريزيدنس
Project number
2575
Site inspections
7

Schedule

The register lists Stonehenge Residences as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 January 2026

100%+1.6 pts

  • Stonehenge Residences construction site, inspection photo 1, 22 January 2026
  • Stonehenge Residences construction site, inspection photo 2, 22 January 2026
  • Stonehenge Residences construction site, inspection photo 3, 22 January 2026
  • Stonehenge Residences construction site, inspection photo 4, 22 January 2026

17 December 2025

98%+5.4 pts

  • Stonehenge Residences construction site, inspection photo 1, 17 December 2025
  • Stonehenge Residences construction site, inspection photo 2, 17 December 2025
  • Stonehenge Residences construction site, inspection photo 3, 17 December 2025
  • Stonehenge Residences construction site, inspection photo 4, 17 December 2025

5 May 2025

93%+21 pts

  • Stonehenge Residences construction site, inspection photo 1, 5 May 2025
  • Stonehenge Residences construction site, inspection photo 2, 5 May 2025
  • Stonehenge Residences construction site, inspection photo 3, 5 May 2025
  • Stonehenge Residences construction site, inspection photo 4, 5 May 2025

15 January 2025

72%+21 pts

  • Stonehenge Residences construction site, inspection photo 1, 15 January 2025
  • Stonehenge Residences construction site, inspection photo 2, 15 January 2025
  • Stonehenge Residences construction site, inspection photo 3, 15 January 2025
  • Stonehenge Residences construction site, inspection photo 4, 15 January 2025

14 October 2024

51%+31 pts

  • Stonehenge Residences construction site, inspection photo 1, 14 October 2024
  • Stonehenge Residences construction site, inspection photo 2, 14 October 2024
  • Stonehenge Residences construction site, inspection photo 3, 14 October 2024
  • Stonehenge Residences construction site, inspection photo 4, 14 October 2024

28 March 2024

20%+20 pts

  • Stonehenge Residences construction site, inspection photo 1, 28 March 2024
  • Stonehenge Residences construction site, inspection photo 2, 28 March 2024
  • Stonehenge Residences construction site, inspection photo 3, 28 March 2024
  • Stonehenge Residences construction site, inspection photo 4, 28 March 2024

8 March 2023

0.1%

  • Stonehenge Residences construction site, inspection photo 1, 8 March 2023
  • Stonehenge Residences construction site, inspection photo 2, 8 March 2023
  • Stonehenge Residences construction site, inspection photo 3, 8 March 2023
  • Stonehenge Residences construction site, inspection photo 4, 8 March 2023

All 62 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Stonehenge Residences?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Stonehenge Residences handover date?
Construction of Stonehenge Residences is recorded as complete, with a registered completion date of March 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Stonehenge Residences?
Stonehenge Residences was 100% built at the site inspection on 22 January 2026. The site has been inspected 7 times since March 2023. The Land Department took 62 site photos at its inspections.
Is Stonehenge Residences delayed?
The register lists construction as complete.
Who is building Stonehenge Residences?
The registered developer is Segrex Development.
Which bank holds the escrow account for Stonehenge Residences?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.