Stax construction progress

Stax in Jumeirah Village Circle is 4.5% built at the Land Department inspection of July 2026. Developer Pashaone Real Estate Development. Completion registered for March 2028.

4.5%

Built, at the Land Department site inspection of 24 July 2026

Running behind its date

Completion date (Land Department)
March 2028
Finish at recent pace
May 2047
Construction started
November 2025
Registered with the Land Department
September 2025
Developer
Pashaone Real Estate Development
Units
530
Escrow bank
First Abu Dhabi Bank
Name in Arabic
استاكس
Land Department project number
4013
Land Department site inspections
3

Schedule

Between July 2025 and July 2026 the site added about 0.4 points a month. At that rate it would finish around May 2047, more than three months after the March 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

24 July 2026

4.5%+3.8 pts

  • Stax construction site, Land Department inspection photo 1, 24 July 2026
  • Stax construction site, Land Department inspection photo 2, 24 July 2026
  • Stax construction site, Land Department inspection photo 3, 24 July 2026

14 April 2026

0.7%+0.7 pts

  • Stax construction site, Land Department inspection photo 1, 14 April 2026
  • Stax construction site, Land Department inspection photo 2, 14 April 2026
  • Stax construction site, Land Department inspection photo 3, 14 April 2026

31 July 2025

0%

  • Stax construction site, Land Department inspection photo 1, 31 July 2025
  • Stax construction site, Land Department inspection photo 2, 31 July 2025

All 8 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Own a unit in Stax?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Stax be completed?
The completion date registered with the Dubai Land Department is March 2028. At the pace of its recent inspections the site would reach 100% around May 2047. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Stax is built?
4.5%, measured at the Land Department site inspection on 24 July 2026. The Land Department engineers have inspected the site 3 times since July 2025.
Is Stax delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Stax?
The registered developer is Pashaone Real Estate Development.
Which bank holds the escrow account for Stax?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.