Stax construction progress

The registered completion date for Stax in Jumeirah Village Circle is March 2028. At the last site inspection, in October 2026, it was 5.7% built. The developer is Pashaone Real Estate Development.

5.7%

Built, at the site inspection of 27 October 2026

Running behind its date

Registered completion date
March 2028
Finish at recent pace
December 2036
Construction started
November 2025
First registered
September 2025
Developer
Pashaone Real Estate Development
Units
530
Escrow bank
First Abu Dhabi Bank
Name in Arabic
استاكس
Project number
4013
Site inspections
4

Schedule

Between April 2026 and October 2026 the site added about 0.8 points a month. At that rate it would finish around December 2036, more than three months after its registered date of March 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 October 2026

5.7%+1.2 pts

  • Stax construction site, inspection photo 1, 27 October 2026
  • Stax construction site, inspection photo 2, 27 October 2026
  • Stax construction site, inspection photo 3, 27 October 2026

24 July 2026

4.5%+3.8 pts

  • Stax construction site, inspection photo 1, 24 July 2026
  • Stax construction site, inspection photo 2, 24 July 2026
  • Stax construction site, inspection photo 3, 24 July 2026

14 April 2026

0.7%+0.7 pts

  • Stax construction site, inspection photo 1, 14 April 2026
  • Stax construction site, inspection photo 2, 14 April 2026
  • Stax construction site, inspection photo 3, 14 April 2026

31 July 2025

0%

  • Stax construction site, inspection photo 1, 31 July 2025
  • Stax construction site, inspection photo 2, 31 July 2025

All 11 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Stax?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Stax handover date?
The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Stax?
Stax was 5.7% built at the site inspection on 27 October 2026. The site has been inspected 4 times since July 2025. The Land Department took 11 site photos at its inspections.
Is Stax delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Stax?
The registered developer is Pashaone Real Estate Development.
Which bank holds the escrow account for Stax?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.