Sky Suites By Peace Homes construction progress

Sky Suites By Peace Homes in Jumeirah Village Circle is 56% built at the Land Department inspection of July 2026. Developer Peace Homes Signatures Development. Completion registered for December 2025.

56%

Built, at the Land Department site inspection of 27 July 2026

10 months past its registered completion date

Completion date (Land Department)
December 2025
Finish at recent pace
September 2027
Construction started
September 2023
Registered with the Land Department
June 2023
Developer
Peace Homes Signatures Development
Units
239
Escrow bank
Mashreq Bank
Name in Arabic
سكاي سويتس باي بيس هومز
Land Department project number
2665
Land Department site inspections
6

Schedule

Sky Suites By Peace Homes was registered to complete in December 2025, 10 months ago, and is still under construction. Over the last year of inspections it has added about 3.3 points a month. Kept at that rate, the site would reach 100% around September 2027.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

27 July 2026

56%+22 pts

  • Sky Suites By Peace Homes construction site, Land Department inspection photo 1, 27 July 2026
  • Sky Suites By Peace Homes construction site, Land Department inspection photo 2, 27 July 2026
  • Sky Suites By Peace Homes construction site, Land Department inspection photo 3, 27 July 2026
  • Sky Suites By Peace Homes construction site, Land Department inspection photo 4, 27 July 2026

14 January 2026

34%+9.0 pts

  • Sky Suites By Peace Homes construction site, Land Department inspection photo 1, 14 January 2026
  • Sky Suites By Peace Homes construction site, Land Department inspection photo 2, 14 January 2026
  • Sky Suites By Peace Homes construction site, Land Department inspection photo 3, 14 January 2026
  • Sky Suites By Peace Homes construction site, Land Department inspection photo 4, 14 January 2026

15 October 2025

25%+20 pts

  • Sky Suites By Peace Homes construction site, Land Department inspection photo 1, 15 October 2025
  • Sky Suites By Peace Homes construction site, Land Department inspection photo 2, 15 October 2025
  • Sky Suites By Peace Homes construction site, Land Department inspection photo 3, 15 October 2025
  • Sky Suites By Peace Homes construction site, Land Department inspection photo 4, 15 October 2025

30 June 2024

4.8%+1.6 pts

  • Sky Suites By Peace Homes construction site, Land Department inspection photo 1, 30 June 2024
  • Sky Suites By Peace Homes construction site, Land Department inspection photo 2, 30 June 2024
  • Sky Suites By Peace Homes construction site, Land Department inspection photo 3, 30 June 2024
  • Sky Suites By Peace Homes construction site, Land Department inspection photo 4, 30 June 2024

17 May 2024

3.2%+0.3 pts

  • Sky Suites By Peace Homes construction site, Land Department inspection photo 1, 17 May 2024
  • Sky Suites By Peace Homes construction site, Land Department inspection photo 2, 17 May 2024
  • Sky Suites By Peace Homes construction site, Land Department inspection photo 3, 17 May 2024
  • Sky Suites By Peace Homes construction site, Land Department inspection photo 4, 17 May 2024

15 May 2023

2.9%

  • Sky Suites By Peace Homes construction site, Land Department inspection photo 1, 15 May 2023
  • Sky Suites By Peace Homes construction site, Land Department inspection photo 2, 15 May 2023

All 39 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Own a unit in Sky Suites By Peace Homes?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Sky Suites By Peace Homes be completed?
The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around September 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Sky Suites By Peace Homes is built?
56%, measured at the Land Department site inspection on 27 July 2026. The Land Department engineers have inspected the site 6 times since May 2023.
Is Sky Suites By Peace Homes delayed?
Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
Who is building Sky Suites By Peace Homes?
The registered developer is Peace Homes Signatures Development.
Which bank holds the escrow account for Sky Suites By Peace Homes?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.