Serenity Lakes 2 construction progress
Serenity Lakes 2 in Jumeirah Village Circle is 50% built at the Land Department inspection of September 2026. Developer Gulf Land Property Developers. Completion registered for November 2025.
50%
Built, at the Land Department site inspection of 11 September 2026
11 months past its registered completion date
- Completion date (Land Department)
- November 2025
- Finish at recent pace
- July 2032
- Construction started
- June 2014
- Registered with the Land Department
- August 2014
- Developer
- Gulf Land Property Developers
- Community
- Jumeirah Village Circle
- Units
- 268
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- بحيرات الصفاء 2
- Land Department project number
- 1555
- Land Department site inspections
- 12
Schedule
Serenity Lakes 2 was registered to complete in November 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 0.7 points a month. Kept at that rate, the site would reach 100% around July 2032.
Site inspections
11 September 2026
50%+0.5 pts
2 July 2026
50%+2.7 pts
25 April 2026
47%
22 July 2024
47%+6.8 pts
8 May 2023
40%+1.0 pts
14 April 2022
39%
29 April 2019
39%+11 pts
26 February 2018
28%+12 pts
20 September 2017
17%+5.6 pts
11 April 2017
11%+7.8 pts
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average. Serenity Lakes 2 is ahead of that average.
Gulf Land Property Developers has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Serenity Lakes 2?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Serenity Lakes 2 be completed?
- The completion date registered with the Dubai Land Department is November 2025. At the pace of its recent inspections the site would reach 100% around July 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Serenity Lakes 2 is built?
- 50%, measured at the Land Department site inspection on 11 September 2026. The Land Department engineers have inspected the site 12 times since July 2015.
- Is Serenity Lakes 2 delayed?
- Yes. Its registered completion date of November 2025 has passed and the Land Department still lists it as under construction.
- Who is building Serenity Lakes 2?
- The registered developer is Gulf Land Property Developers. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Serenity Lakes 2?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Tonino Lamborghini ResidencesAlso by Gulf Land Property Developers. 60%, Due December 2026.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Luxury Family ResidenceNearby in Jumeirah Village Circle. 76%, Due December 2023, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.