Serenity Lakes 2 construction progress

Serenity Lakes 2 in Jumeirah Village Circle is 50% built at the Land Department inspection of September 2026. Developer Gulf Land Property Developers. Completion registered for November 2025.

50%

Built, at the Land Department site inspection of 11 September 2026

11 months past its registered completion date

Completion date (Land Department)
November 2025
Finish at recent pace
July 2032
Construction started
June 2014
Registered with the Land Department
August 2014
Developer
Gulf Land Property Developers
Units
268
Escrow bank
First Abu Dhabi Bank
Name in Arabic
بحيرات الصفاء 2
Land Department project number
1555
Land Department site inspections
12

Schedule

Serenity Lakes 2 was registered to complete in November 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 0.7 points a month. Kept at that rate, the site would reach 100% around July 2032.

0%25%50%75%100%2015201820212024
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

11 September 2026

50%+0.5 pts

  • Serenity Lakes 2 construction site, Land Department inspection photo 1, 11 September 2026
  • Serenity Lakes 2 construction site, Land Department inspection photo 2, 11 September 2026
  • Serenity Lakes 2 construction site, Land Department inspection photo 3, 11 September 2026
  • Serenity Lakes 2 construction site, Land Department inspection photo 4, 11 September 2026

2 July 2026

50%+2.7 pts

  • Serenity Lakes 2 construction site, Land Department inspection photo 1, 2 July 2026
  • Serenity Lakes 2 construction site, Land Department inspection photo 2, 2 July 2026
  • Serenity Lakes 2 construction site, Land Department inspection photo 3, 2 July 2026
  • Serenity Lakes 2 construction site, Land Department inspection photo 4, 2 July 2026

25 April 2026

47%

  • Serenity Lakes 2 construction site, Land Department inspection photo 1, 25 April 2026
  • Serenity Lakes 2 construction site, Land Department inspection photo 2, 25 April 2026
  • Serenity Lakes 2 construction site, Land Department inspection photo 3, 25 April 2026
  • Serenity Lakes 2 construction site, Land Department inspection photo 4, 25 April 2026

22 July 2024

47%+6.8 pts

  • Serenity Lakes 2 construction site, Land Department inspection photo 1, 22 July 2024
  • Serenity Lakes 2 construction site, Land Department inspection photo 2, 22 July 2024
  • Serenity Lakes 2 construction site, Land Department inspection photo 3, 22 July 2024
  • Serenity Lakes 2 construction site, Land Department inspection photo 4, 22 July 2024

8 May 2023

40%+1.0 pts

  • Serenity Lakes 2 construction site, Land Department inspection photo 1, 8 May 2023
  • Serenity Lakes 2 construction site, Land Department inspection photo 2, 8 May 2023
  • Serenity Lakes 2 construction site, Land Department inspection photo 3, 8 May 2023
  • Serenity Lakes 2 construction site, Land Department inspection photo 4, 8 May 2023

14 April 2022

39%

  • Serenity Lakes 2 construction site, Land Department inspection photo 1, 14 April 2022
  • Serenity Lakes 2 construction site, Land Department inspection photo 2, 14 April 2022
  • Serenity Lakes 2 construction site, Land Department inspection photo 3, 14 April 2022
  • Serenity Lakes 2 construction site, Land Department inspection photo 4, 14 April 2022

29 April 2019

39%+11 pts

  • Serenity Lakes 2 construction site, Land Department inspection photo 1, 29 April 2019
  • Serenity Lakes 2 construction site, Land Department inspection photo 2, 29 April 2019
  • Serenity Lakes 2 construction site, Land Department inspection photo 3, 29 April 2019
  • Serenity Lakes 2 construction site, Land Department inspection photo 4, 29 April 2019

26 February 2018

28%+12 pts

  • Serenity Lakes 2 construction site, Land Department inspection photo 1, 26 February 2018
  • Serenity Lakes 2 construction site, Land Department inspection photo 2, 26 February 2018
  • Serenity Lakes 2 construction site, Land Department inspection photo 3, 26 February 2018
  • Serenity Lakes 2 construction site, Land Department inspection photo 4, 26 February 2018

20 September 2017

17%+5.6 pts

  • Serenity Lakes 2 construction site, Land Department inspection photo 1, 20 September 2017
  • Serenity Lakes 2 construction site, Land Department inspection photo 2, 20 September 2017
  • Serenity Lakes 2 construction site, Land Department inspection photo 3, 20 September 2017

11 April 2017

11%+7.8 pts

  • Serenity Lakes 2 construction site, Land Department inspection photo 1, 11 April 2017

All 68 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average. Serenity Lakes 2 is ahead of that average.

Gulf Land Property Developers has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Serenity Lakes 2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Serenity Lakes 2 be completed?
The completion date registered with the Dubai Land Department is November 2025. At the pace of its recent inspections the site would reach 100% around July 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Serenity Lakes 2 is built?
50%, measured at the Land Department site inspection on 11 September 2026. The Land Department engineers have inspected the site 12 times since July 2015.
Is Serenity Lakes 2 delayed?
Yes. Its registered completion date of November 2025 has passed and the Land Department still lists it as under construction.
Who is building Serenity Lakes 2?
The registered developer is Gulf Land Property Developers. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Serenity Lakes 2?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.