Serenity Lakes 2 construction photos
68 photos taken by Dubai Land Department engineers at 12 site inspections, newest first. The percentage is how much of Serenity Lakes 2 was built on the day of each visit.
11 September 202650% built
2 July 202650% built
25 April 202647% built
22 July 202447% built
8 May 202340% built
14 April 202239% built
29 April 201939% built
26 February 201828% built
20 September 201717% built
11 April 201711% built
8 October 20153.5% built
14 July 20152.3% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.