Rose Gold Residences By Zee Development construction progress
Rose Gold Residences By Zee Development in Jumeirah Village Circle is 0% built at the Land Department inspection of April 2025. Developer Zee Development. Completion registered for January 2028.
0%
Built, at the Land Department site inspection of 22 April 2025
- Completion date (Land Department)
- January 2028
- Construction started
- August 2025
- Registered with the Land Department
- September 2025
- Developer
- Zee Development
- Community
- Jumeirah Village Circle
- Units
- 175
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- روز جولد رزيدينسز باي زيي ديفيلوبمنت
- Land Department project number
- 3677
- Land Department site inspections
- 1
Schedule
The Land Department has inspected Rose Gold Residences By Zee Development once so far, which is not enough to measure a pace. A pace needs two inspections at least a month apart.
Site inspections
22 April 2025
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Own a unit in Rose Gold Residences By Zee Development?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Rose Gold Residences By Zee Development be completed?
- The completion date registered with the Dubai Land Department is January 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Rose Gold Residences By Zee Development is built?
- 0%, measured at the Land Department site inspection on 22 April 2025.
- Who is building Rose Gold Residences By Zee Development?
- The registered developer is Zee Development.
- Which bank holds the escrow account for Rose Gold Residences By Zee Development?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.

