Provenza Residences construction progress

The registered completion date for Provenza Residences in Jumeirah Village Circle is September 2027. At the last site inspection, in August 2026, it was 20% built. The developer is I K R Real Estate Development.

20%

Built, at the site inspection of 6 August 2026

Running behind its date

Registered completion date
September 2027
Finish at recent pace
April 2029
Construction started
July 2025
First registered
May 2025
Developer
I K R Real Estate Development
Units
188
Escrow bank
Mashreq Bank
Name in Arabic
مساكن بروفينزا
Project number
3681
Site inspections
3

Schedule

Between May 2026 and August 2026 the site added about 2.5 points a month. At that rate it would finish around April 2029, more than three months after its registered date of September 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 August 2026

20%+6.5 pts

  • Provenza Residences construction site, inspection photo 1, 6 August 2026
  • Provenza Residences construction site, inspection photo 2, 6 August 2026
  • Provenza Residences construction site, inspection photo 3, 6 August 2026
  • Provenza Residences construction site, inspection photo 4, 6 August 2026

19 May 2026

14%+14 pts

  • Provenza Residences construction site, inspection photo 1, 19 May 2026
  • Provenza Residences construction site, inspection photo 2, 19 May 2026
  • Provenza Residences construction site, inspection photo 3, 19 May 2026
  • Provenza Residences construction site, inspection photo 4, 19 May 2026

22 April 2025

0%

  • Provenza Residences construction site, inspection photo 1, 22 April 2025
  • Provenza Residences construction site, inspection photo 2, 22 April 2025

All 14 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Own a unit in Provenza Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Provenza Residences handover date?
The registered completion date is September 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Provenza Residences?
Provenza Residences was 20% built at the site inspection on 6 August 2026. The site has been inspected 3 times since April 2025. The Land Department took 14 site photos at its inspections.
Is Provenza Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2027.
Who is building Provenza Residences?
The registered developer is I K R Real Estate Development.
Which bank holds the escrow account for Provenza Residences?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.